Certified Construction Quality Manager Questions and Answers

Question 9

Within a quality management plan, quality audits are defined as

Options:

A.

an optional activity based on available resources

B.

a method to assess the financial aspects of the project

C.

a systematic process to verify compliance with quality standards

D.

a single review at the end of a project

Question 10

Which of the following is a likely consequence of failing to properly assess inspection and test records for safety-critical equipment at project closeout?

Options:

A.

Increased innovation in project processes

B.

Enhanced team collaboration

C.

Discovery of non-compliance with safety standards

D.

Improved project scheduling efficiency

Question 11

Corrective strategies implemented to resolve customer complaints in a construction project should

Options:

A.

assume any decrease in complaints indicates a successful strategy

B.

evaluate the effectiveness based on the speed of complaint resolution

C.

measure customer satisfaction before and after the implementation of corrective actions

D.

rely on customer testimonials as the measure of strategy success

Question 12

When evaluating materials for a construction project, which approach ensures they conform to project specifications?

Options:

A.

Conducting inspections according to project quality standards

B.

Selecting materials based on the lowest cost available

C.

Relying on the supplier's reputation to ensure quality

D.

Choosing materials for their ease of installation