Weekend Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

CQE Exam Results

Page: 7 / 13
Total 175 questions

Certified Quality EngineerExam Questions and Answers

Question 25

Which of the following types of planning uses a strategic planning process that relates idealistic goals to work strategy?

Options:

A.

Yoji planning

B.

Hoshin planning

C.

Juran planning

D.

Deining planning

Question 26

An increase in the overall length of a recently qualified metal component has been observed and the quality engineer suspects that the storage temperature could be a factor that has affected the overall length. Which of the following tools could be used to assess this relationship?

Options:

A.

Affinity diagram

B.

Scatter diagram

C.

Histogram

D.

Cause and effect diagram

Question 27

When subgroups are selected in a way that minimizes the opportunity for variation within a subgroup and maximizes the opportunity to detect variation between subgroups, this subgrouping is known as

Options:

A.

random

B.

assignable

C.

controlled

D.

rational

Question 28

According to ANSI ASQ Z1.4. switching from tightened inspection to normal inspection can occur when how many consecutive lots have been accepted?

Options:

A.

Four out of five

B.

Five out of five

C.

Eight out of ten

D.

Nine out of ten

Page: 7 / 13
Total 175 questions