The compilation and storage of lessons learned for a completed project can be used to:
To meet the requirements of the project through effective contract management, it is best to:
Which data can be imported directly from 4C into PPR?
Which of these key performance indicators (KPIs) supports the identification of possible cost overruns?
Which of the following is NOT part of the IPM suite?
Which of the following examples are effective results of a correctly performed root cause analysis?
During which stage of risk planning are risks prioritized based on probability and impact?
What obligations towards the F&C community does the cost and progress manager have in regards to costs?
When a Customer Contract is not yet signed and a purchase order has not yet been received, in which circumstances can a service be subcontracted?
Which is not a factor in choosing a subcontractor?
The product line is unable to meet a software release committed timeline. Due to this delay, resources dedicated to the installation need to remain available for an additional month. Additionally, the project will be liable to pay penalties based on contract conditions. How should these extra costs be reported?
What activity is the final stage before input of the planned project costs to 4C?
What are the two key elements to calculate the project cost adherence (PCA)?
A risk response which involves eliminating a threat is called:
During project execution, a large number of changes are made to the project. The project manager should:
In Nokia, what does PARD stands for?
The Resource Breakdown Structure (RBS) is a:
What is the primary KPI generated from the Site Quality module of IPM?
What of the following cost components is NOT included in the CBL?
The risk contingency reserve is identified in which process?
What is the impact if procurement renegotiates longer payment terms with our supplier?
What is the best timing to review the estimate at completion (EAC)?
Your customer's Care contract expired at the end of last year. No purchase orders have been received from the customer since the contract expired. How can Care service revenue be recognized in this case?
When must the change management process be initiated?
For which of the following reasons can the cost baseline be updated?
As theoretically defined, what characteristic best describes the cost baseline?
What approval process is required when the EAC deviates >2% from the CBL?
The WBS comprises several levels of decomposition of the total project. The lowest level of definition is always the:
The one document that should always be used to identify and mitigate risk is the:
Which of the following is a direct project cost?