Weekend Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Nokia Networks Certification PDM_2002001060 Updated Exam

CPM Questions and Answers

Question 25

When must the change management process be initiated?

Options:

A.

When there is a significant change in the scope of the project.

B.

When the customer sends a formal request for additional scope of work.

C.

When the CT head acknowledges that the customer will accept negotiation of the changes in the scope of the contract.

D.

Whenever the project execution requires services or materials different from those agreed in the contractual scope of work.

Question 26

For which of the following reasons can the cost baseline be updated?

Options:

A.

Due to cost savings.

B.

Due to delays in project execution.

C.

Due to customer driven scope change.

D.

Due to subcontractor's price change.

Question 27

As theoretically defined, what characteristic best describes the cost baseline?

Options:

A.

Total budget for the project.

B.

Time phased budget for the project.

C.

Total budget for the project including the contingency budget.

D.

Total budget for the project including the contingency budget and the management reserve.

Question 28

What approval process is required when the EAC deviates >2% from the CBL?

Options:

A.

The CT starts the LoA approval process and if the LoA approves the cost increase, the initial CBL is updated.

B.

The CT starts the LoA approval process and if the LoA approves the cost increase, the initial CBL is not updated, but the EAC will be updated to reflect the change.

C.

The COM requests approval from CBC and if the CBC approves the cost increase, the initial CBL is not updated, but the EAC will be updated to reflect the change.

D.

The COM requests approval from CBC and if the CBC approves the cost increase, the initial CBL is updated.