The WBS comprises several levels of decomposition of the total project. The lowest level of definition is always the:
build cycle.
planning element.
working interface.
work package.
The one document that should always be used to identify and mitigate risk is the:
risk management plan.
scope statement.
project charter.
contingency plan.
Which of the following is a direct project cost?
Corporate office utilities.
Workers compensation insurance.
Installation materials.
Both corporate office utilities and workers compensation insurance.