Question 29

The WBS comprises several levels of decomposition of the total project. The lowest level of definition is always the:

Options:

A.

build cycle.

B.

planning element.

C.

working interface.

D.

work package.

Question 30

The one document that should always be used to identify and mitigate risk is the:

Options:

A.

risk management plan.

B.

scope statement.

C.

project charter.

D.

contingency plan.

Question 31

Which of the following is a direct project cost?

Options:

A.

Corporate office utilities.

B.

Workers compensation insurance.

C.

Installation materials.

D.

Both corporate office utilities and workers compensation insurance.