When does a Developer become accountable for an item in the Sprint Backlog?
(choose the best answer)
During the Daily Scrum.
As soon as a Developer on the Scrum Team can accommodate more work.
Never. All Developers on the Scrum Team share accountability for items in the Sprint
Backlog.
At Sprint Planning when all of the Sprint Backlog items are split evenly across the
Developers.
The Developers on the Scrum Team share accountability for the Sprint Backlog, which is a forecast of the work and the plan to deliver the Sprint Goal12. The Sprint Backlog is dynamic and can be updated by the Developers as more is learned during the Sprint34. The Developers are not individually accountable for the items in the Sprint Backlog, nor are they assigned by the Scrum Master or the Product Owner5.
Scrum requires that the Product Owner must use which of the following items?
(choose all that apply)
Burndown chart.
Feature burn-up.
Critical Path Analysis.
Project Gantt chart.
None of the above.
Scrum does not require that the Product Owner must use any of the following items:
Therefore, the correct answer is none of the above.
References:
Who is on the Scrum Team?
(choose all that apply)
Scrum Master.
Product Owner.
Developers.
Project Manager.
None of the above.
The Scrum Team consists of one Scrum Master, one Product Owner, and Developers. Within a Scrum Team, there are no sub-teams or hierarchies. It is a cohesive unit of professionals focused on one objective at a time, the Product Goal. The Scrum Master is accountable for establishing Scrum as defined in the Scrum Guide. They do this by helping everyone understand Scrum theory and practice, both within the Scrum Team and the organization. The Product Owner is accountable for maximizing the value of the product resulting from the work of the Scrum Team. They are responsible for creating and communicating a vision, ordering the Product Backlog, and ensuring that the best possible job is done to delight customers. The Developers are the people in the Scrum Team that are committed to delivering a “Done” Increment that meets the Definition of Done and the Sprint Goal. They are responsible for managing and organizing their work within the Sprint, collaborating with the Product Owner and the Scrum Master, and applying their skills and creativity to create a product that delivers value to the stakeholders and customers. A Project Manager is not a role in the Scrum Team, as Scrum does not recognize titles for Developers, regardless of the work being performed by the person. There is no need for a Project Manager, as the Scrum Team is self-managing and accountable for delivering value.
References:
True or False: The Product Owner should have the entire Product Backlog documented in detail before the first Sprint can start?
True
False
The Product Owner should not have the entire Product Backlog documented in detail before the first Sprint can start. This is because:
References:
Which of the following is an example of an Increment?
(choose the best answer)
A plan for the overall product release.
A mock-up of the product marketing materials.
A design for the product.
A product roll-out plan.
A valuable, useful set of product features.
All of the above.
An Increment is the sum of all the Product Backlog items completed during a Sprint and the value of the increments of all previous Sprints.1 An Increment is a concrete, tangible, and usable outcome of the work done by the Developers in a Sprint. It is not a plan, a mock-up, a design, or a roll-out plan, as these are not valuable or useful products in themselves. An Increment must meet the definition of “Done”, which means it must adhere to the quality standards agreed upon by the Scrum Team and the stakeholders.1 An Increment must also be potentially releasable, which means it must be in a state that it could be delivered to the customer or user if the Product Owner decides so.1
References:
What may be included in the Sprint Backlog?
(choose the best answer)
User Stories.
Tasks.
Use Cases.
Tests.
Any of the above (or others) which are a decomposition of the selected Product
Backlog items.
The Sprint Backlog is the set of Product Backlog items selected for the Sprint, plus a plan for delivering the product Increment and realizing the Sprint Goal1. The Sprint Backlog is a forecast by the Developers about what functionality will be in the next Increment and the work needed to deliver that functionality into a “Done” Increment1. The Sprint Backlog makes visible all the work that the Developers identify as necessary to meet the Sprint Goal1. The Sprint Backlog can include any items that the Developers deem necessary to achieve the Sprint Goal, such as user stories, tasks, use cases, tests, or others. The Sprint Backlog is a plan with enough detail that changes in progress can be understood in the Daily Scrum1.
References:
What tactic should a Scrum Team use to divide a group of 100 people into multiple Scrum
Teams?
(choose the best answer)
Ask the people to divide themselves into teams.
Create teams based on their skills across multiple layers (such as database, UI,
etc.).
Ask the Product Owner to assign the people to teams.
According to Scrum.org, when splitting a large group into multiple Scrum Teams, it can be beneficial to allow the people to self-organize into smaller teams12. This approach respects the principle of self-organization, which is a key aspect of Scrum12. It allows individuals to choose the team they feel they can contribute to most effectively12. However, it’s important to note that this process should be facilitated and guided to ensure a balanced distribution of skills and capabilities across the teams12.
Scrum is based on empiricism. All of its artifacts must be transparent to ensure sufficient accuracy of inspection. How can the Scrum Team maintain the Product Backlog to maximize its transparency?
(choose the best answer)
The Product Backlog is only updated at the Sprint Review, when both the Scrum
Team and the stakeholders are available.
Product Backlog items should hold no more than 8 points of work, which is the
average in the range of acceptable sizes of 1, 2, 3, 5, 8, and 13.
Product Backlog items must be sized such that the highest ordered items are no bigger than a Sprint.
The Product Backlog is only updated at a release planning meeting with the
stakeholders and the change control board present.
The Product Backlog is continually kept up to date with the most recent insights.
The Scrum Team can maintain the Product Backlog to maximize its transparency by continually keeping it up to date with the most recent insights because:
References:
Which metrics will help a Product Owner determine if a product is delivering value?
(choose the best two answers)
Customer satisfaction.
Productivity.
Velocity.
Time to market.
Percentage of scope implemented.
The metrics that will help a Product Owner determine if a product is delivering value are customer satisfaction and time to market. This is because:
Other metrics, such as productivity, velocity, and percentage of scope implemented, are not directly related to value delivery. They may indicate how efficiently or effectively the Scrum Team is working, but they do not necessarily reflect how valuable or desirable the product is for the customers or stakeholders.
References:
True or False: Product Owners must specify complete acceptance criteria for a Product
Backlog item before the Developers can select the item in Sprint Planning.
True
False
Answer: False
Very Short Explanation: According to Scrum.org, the Product Owner is not required to create clear and unambiguous acceptance criteria for each item in the product’s backlog before it can be selected in Sprint Planning1. Acceptance Criteria is optional and is not prescribed by Scrum12. It can be valuable, but it’s not a must12. The Developers can inspect and adapt the Sprint Backlog in any way they see fit, in order to help meet the Sprint Goal2.
True or False: Sprint Reviews are an opportunity to collect stakeholder feedback.
True
False
References:
What is the responsibility of the Product Owner in crafting the Sprint Goal?
(choose the best answer)
The Product Owner has no responsibility for the Sprint Goal. It is the sole
responsibility of the Developers.
The Product Owner cannot attend Sprint Planning without having documented the
Sprint Goal in advance.
The Product Owner should come to Sprint Planning with a business objective in mind and work with the Developers to craft the Sprint Goal.
The Product Owner must work with stakeholders to set each Sprint's Goal.
The Product Owner defines the scope for a Sprint and therefore also the Sprint Goal.
References:
What are two effective ways for the Scrum Team to make non-functional requirements visible?
(choose the best two answers)
Add them to the Product Backlog to ensure transparency.
Run the integration and regression tests before the end of the Sprint, and
capture the open work for the Sprint Backlog of the next Sprint.
Add them to the Definition of Done so the work is taken care of every Sprint.
Put them on a separate list on the Scrum board, available for all to see.
Non-functional requirements are the criteria that define the quality, performance, security, usability, and other aspects of a product1. They are often implicit or assumed, but they are important to make visible and explicit, as they affect the value and satisfaction of the product2. One effective way to make non-functional requirements visible is to add them to the Product Backlog, which is an ordered list of everything that is known to be needed in the product[3][3]. By adding non-functional requirements to the Product Backlog, the Product Owner and the Developers can prioritize, refine, and estimate them, and make them transparent to the stakeholders4. Another effective way to make non-functional requirements visible is to add them to the Definition of Done, which is a shared understanding of what it means for work to be complete, and ensures transparency of the quality of the work done5. By adding non-functional requirements to the Definition of Done, the Developers can ensure that every Product Backlog item and Increment meets the expected quality standards, and that the work is taken care of every Sprint.
References:
1: Non-functional requirement, Wikipedia, accessed on December 16, 2023
2: Managing Products with Agility, Scrum.org, accessed on December 16, 2023
[3][3]: The Scrum Guide, November 2020, p. 6
4: The Scrum Guide, November 2020, p. 7
5: The Scrum Guide, November 2020, p. 13
Understanding and Applying the Scrum Framework, Scrum.org, accessed on December 16, 2023
When does a Sprint conclude?
(choose the best answer)
When all the tasks are completed by the Developers.
When the Sprint Retrospective is complete.
When all Product Backlog items meet their Definition of Done.
When the Product Owner decides enough has been delivered to meet the Sprint
Goal.
A Sprint is a time-boxed period when a Scrum Team works to complete a set amount of work that delivers value to the customer1. A Sprint concludes when the time-box expires, regardless of whether all the tasks, Product Backlog items, or Definition of Done are completed or not23. The Product Owner has the authority to cancel a Sprint if they determine that the Sprint Goal is obsolete or the work done is no longer valuable1. Therefore, the Product Owner decides when enough has been delivered to meet the Sprint Goal, and the Sprint ends accordingly.
Which of the following are appropriate topics for discussion during a Sprint Retrospective?
(choose the best two answers)
Identifying high priority process improvements for the next Sprint.
The order of items in the Product Backlog.
How the team collaborates.
Documenting acceptance criteria for items in the next Sprint.
The Sprint Retrospective is an event for the Scrum Team to inspect how the last Sprint went with regards to individuals, interactions, processes, tools, and their Definition of Done1. The purpose of the Sprint Retrospective is to plan ways to increase quality and effectiveness for the next Sprint2. Therefore, appropriate topics for discussion during a Sprint Retrospective are:
Identifying high priority process improvements for the next Sprint. The Scrum Team should identify the most important things that went well and the potential improvements, and create a plan for implementing some of them in the next Sprint[3][3]. This way, the Scrum Team can continuously improve their performance and deliver more value.
How the team collaborates. The Scrum Team should reflect on how they work together as a self-managing unit, and how they can enhance their skills, tools, and relationships4. This way, the Scrum Team can foster a culture of trust, respect, and collaboration.
The other options are not appropriate topics for discussion during a Sprint Retrospective, as they are either related to the Product Backlog or the Sprint Backlog, which are not the focus of the Sprint Retrospective. The order of items in the Product Backlog is the responsibility of the Product Owner, who manages the Product Backlog based on the value, risk, and dependencies of the items5. The Product Owner may seek input from the Scrum Team or the stakeholders, but the final decision is up to the Product Owner. Documenting acceptance criteria for items in the next Sprint is part of the Product Backlog refinement, which is an ongoing activity throughout the Sprint, not a specific event. The Scrum Team should collaborate on refining the Product Backlog items and adding more details, such as acceptance criteria, as they become more clear and ready for selection in a Sprint Planning.
References:
1: The Scrum Guide, November 2020, p. 14
2: The Scrum Guide, November 2020, p. 15
[3][3]: The Scrum Guide, November 2020, p. 15
4: Developing People and Teams, Scrum.org, accessed on December 16, 2023
5: The Scrum Guide, November 2020, p. 7
The Scrum Guide, November 2020, p. 10
The Scrum Guide, November 2020, p. 10
Understanding and Applying the Scrum Framework, Scrum.org, accessed on December 16, 2023
True or False: The Scrum Team is accountable for creating a valuable increment every Sprint.
True
False
References:
True or False: Every Scrum Team must have a Product Owner and Scrum Master.
False. A Scrum Master is only required when asked for by the Scrum Team.
True. Each must be 100% dedicated to the Scrum Team.
False. A Product Owner can be replaced by a subject matter expert in the Scrum
Team.
True. Outcomes are affected by their participation and availability.
The Product Owner and the Scrum Master are essential roles in the Scrum Team. They have distinct accountabilities and responsibilities that contribute to the success of the product and the team. The Product Owner is responsible for maximizing the value of the product and the work of the Developers. The Scrum Master is responsible for promoting and supporting Scrum and the Scrum Team. Both roles need to be fully engaged and available to the Scrum Team throughout the Sprint.
What typically happens if the Product Backlog is not sufficiently clear at Sprint Planning?
(choose the best answer)
The Product Owner should select the Sprint Goal for the Scrum Team so that work can begin.
The Developers will find it difficult to create a Sprint forecast they are confident they can meet.
Nothing in particular.
The Scrum Master should not allow this to happen. Look for a new Scrum Master and re-start the Sprint.
Sprint Planning is canceled so refinement can be done first.
If the Product Backlog is not sufficiently clear at Sprint Planning, the Developers will find it difficult to create a Sprint forecast they are confident they can meet. This is because:
Other options, such as the Product Owner selecting the Sprint Goal for the Scrum Team so that work can begin, nothing in particular happening, the Scrum Master not allowing this to happen or looking for a new Scrum Master and re-starting the Sprint, or Sprint Planning being canceled so refinement can be done first, are not valid answers as they do not reflect what typically happens or what should happen in Scrum.
References:
How much time must a Product Owner spend with the Developers?
(choose the best answer)
Enough so that the Product Owner is confident the Increment will meet the intended value.
40%, or more if the stakeholders agree.
As much time as the Developers tell the Product Owner to be present.
100%
The Product Owner must spend enough time with the Developers so that they are confident the Increment will meet the intended value. This is because:
Other options, such as 40%, as much time as the Developers tell them to be present, or 100%, are not valid answers as they imply a fixed or arbitrary amount of time that does not reflect the actual needs and dynamics of the product development.
References:
Which two ways of creating Scrum Teams are consistent with Scrum's values?
(choose the best two answers)
Bring all the people together and let them organize into Scrum Teams.
Managers personally re-assign current subordinates to new teams.
Existing teams propose how they would like to go about organizing into the new
structure.
Managers collaborate to assign individuals to specific teams.
The Chief Product Owner determines the new team structures and assignments.
True or False: A Product Owner is essentially the same thing as a traditional Project Manager.
True
False
References:
Why is it important that there is only one Product Owner per product?
(choose the best three answers)
The Scrum Master knows who acts as their backup while on vacation.
It would confuse the stakeholders if they had to work with more than one person.
It is clear who is accountable for the ultimate value of the product.
It helps avoid barriers to effective communication and rapid decision-making.
The Scrum Team always knows who determines the order of the Product
Backlog.
The reasons why it is important that there is only one Product Owner per product are:
Other options, such as the Scrum Master knowing who acts as their backup while on vacation or it would confuse the stakeholders if they had to work with more than one person, are not valid reasons why it is important that there is only one Product Owner per product. They may reflect a misunderstanding of the roles and accountabilities of the Scrum Team or the stakeholders.
References:
What is the purpose of a Sprint Review?
(choose the best answer)
To build team spirit.
To take time to judge the validity of the project.
To inspect the product Increment with the stakeholders and collect feedback on next steps.
To review the Scrum Team's activities and processes during the Sprint.
References:
When might a Sprint be cancelled?
(choose the best answer)
When the Developers determine the product plan is infeasible.
When it becomes clear that not everything will be finished by the end of the Sprint.
When the sales department has an important new opportunity.
When the Sprint Goal becomes obsolete.
A Sprint may be cancelled when the Sprint Goal becomes obsolete. This is because:
Other options, such as when the Developers determine the product plan is infeasible, when it becomes clear that not everything will be finished by the end of the Sprint, or when the sales department has an important new opportunity, are not valid reasons for cancelling a Sprint. They may reflect a misunderstanding of what a Sprint Goal is or how Scrum works.
References:
The Developers find out during the Sprint that they are not likely to build everything they forecast. What would you expect a Product Owner to do?
(choose the best answer)
Skip Product Backlog refinement activities.
Inform management that more Developers are needed.
Change the Sprint Goal.
Re-work the selected Product Backlog items with the Developers to meet the Sprint Goal.
Cancel the Sprint.
If the Developers find out during the Sprint that they are not likely to build everything they forecast, the best response from the Product Owner is to re-work the selected Product Backlog items with the Developers to meet the Sprint Goal. This is because:
Other options, such as skipping Product Backlog refinement activities, informing management that more Developers are needed, changing the Sprint Goal, or canceling the Sprint, are not valid responses from the Product Owner as they do not reflect what should happen in Scrum or how to deal with uncertainty and complexity.
References:
Several Sprints into a project, the Product Owner tells the Scrum Master that a key stakeholder
just started using the product. The stakeholder is unhappy with the quality of the product. What
are two good options for the Scrum Master?
(choose the best two answers)
Coach the Product Owner on how to talk with the Developers about this
concern.
Wait to bring this up until the Sprint Retrospective.
Explain to the Product Owner that it is up to the Developers to decide on
acceptable quality standards.
Encourage the Product Owner to put quality specifications on the Product
Backlog and express the stakeholder's concern to the Developers.
Bring the concern to the testers to improve how the Product is verified.
If a stakeholder is unhappy with the quality of the product, the Scrum Master can coach the Product Owner on how to effectively communicate this concern to the Developers1. The Scrum Master can also encourage the Product Owner to put quality specifications on the Product Backlog1. This allows the Developers to understand the stakeholder’s expectations and work towards meeting them1. The Developers are responsible for building quality into the product, but the stakeholders (through the Product Owner) are responsible for setting what is expected in terms of product and process quality1.
Which of the following is required by Scrum?
(choose the best answer)
Sprint Retrospective.
Developers must stand up at the Daily Scrum.
Sprint Burndown Chart.
Release Planning.
All of the above.
The Sprint Retrospective is one of the five events defined by Scrum. It is a formal opportunity for the Scrum Team to inspect itself and create a plan for improvements to be enacted during the next Sprint. The purpose of the Sprint Retrospective is to adapt the way of working so that it becomes more effective and enjoyable. The other options are not required by Scrum, but may be useful practices depending on the context. Developers do not have to stand up at the Daily Scrum, they can choose any format that works for them. A Sprint Burndown Chart is a common way to visualize the remaining work in a Sprint, but it is not mandated by Scrum. Release Planning is a topic that falls under the broader competency of Managing Products with Agility, but it is not a prescribed event in Scrum.
References:
When should the Product Owner update the project plan?
(choose the best answer)
Before the Sprint Planning to know how much work will have to be done in the Sprint.
The Product Backlog is the plan in Scrum. It is updated as new information and insights emerge.
After the Daily Scrum to ensure an accurate daily overview of project progress.
The project plan must be updated prior to the Sprint Retrospective.
Explanation: The Product Owner is responsible for managing and refining the Product Backlog, which is the single source of truth for the plan of the product development. The Product Backlog is a living artifact that changes as the product and the market evolve. The Product Owner updates the Product Backlog continuously based on feedback, learning, and stakeholder needs. There is no separate project plan document in Scrum.
References:
How is management that is external to the Scrum Team involved in the Daily Scrum?
(choose the best answer)
The Product Owner represents their opinions.
The Scrum Master speaks on their behalf.
Managers are not required at the Daily Scrum.
Management gives an update at the start of each Daily Scrum.
Management that is external to the Scrum Team is not involved in the Daily Scrum because:
References:
True or False: The Product Owner must write all of the Product Backlog items (e.g., user stories, requirements, etc.) on the Product Backlog before handing them over to the Scrum Team.
True
False
It is not true that the Product Owner must write all of the Product Backlog items (e.g. user stories, requirements, etc.) on the Product Backlog before handing them over to the Scrum Team. This is because:
References:
How often should customer satisfaction be measured?
(choose the best answer)
Frequently.
Quarterly.
Daily.
Annually.
References:
An organization has decided to adopt Scrum, but management wants to change the
terminology to fit with terminology already used. What will likely happen if this is done?
(choose the best answer)
Without a new vocabulary as a reminder of the change, very little change may
actually happen.
The organization may not understand what has changed within Scrum and the
benefits of Scrum may be lost.
Management may feel less anxious.
All answers apply.
Who does the work to make sure Product Backlog items conform to the Definition of Done?
(choose the best answer)
The Product Owner.
The Quality Assurance Team.
The Scrum Team.
The Developers.
The Scrum Master.
The work to make sure Product Backlog items conform to the Definition of Done is done by the Developers. This is because:
Other options, such as the Product Owner, the Quality Assurance Team, the Scrum Team, or the Scrum Master, are not responsible for making sure Product Backlog items conform to the Definition of Done. They may have different roles and accountabilities in Scrum, but they do not do the actual work of creating a “Done” Increment.
References:
True or False: The Scrum Team is accountable for creating a valuable increment every Sprint.
True
False
The Scrum Team is accountable for creating a valuable increment every Sprint. The Increment is the sum of all Product Backlog items Done during a Sprint and the value of all the previous Increments. The entire Scrum Team is accountable for creating a valuable and useful Increment every Sprint1. The Product Owner is responsible for maximizing the value of the product resulting from the work of the Scrum Team1. The Developers are responsible for creating a Done Increment that meets the Sprint Goal1. The Scrum Master is responsible for establishing Scrum as defined in the Scrum Guide and helping everyone understand Scrum theory, practices, rules, and values1. References:
What is the timebox for the Sprint Planning event?
(choose the best answer)
Monthly.
Whenever it is done.
8 hours for a one-month Sprint.
4 hours for a one-month Sprint.
References:
Why is the Daily Scrum held at the same time and same place?
(choose the best answer)
The Product Owner demands it.
Rooms are hard to book and must be booked in advance.
The place can be named.
The consistency reduces complexity.
The Daily Scrum is held at the same time and same place because:
References:
When does a Developer become accountable for the value of a Product Backlog item selected for the Sprint?
(choose the best answer)
Whenever a team member can accommodate more work.
At the Sprint Planning Event.
During the Daily Scrum.
Never. The entire Scrum Team is accountable for creating value every Sprint.
Correct Answer: D. Never. The entire Scrum Team is accountable for creating value every Sprint.
Explanation: According to the Scrum Guide, the Scrum Team consists of one Product Owner, one Scrum Master, and Developers. The Scrum Team is responsible for all product-related activities, including delivering a valuable, usable product increment every Sprint. The Product Owner is accountable for maximizing the value of the product and the work of the Developers. The Developers are accountable for creating a plan for the Sprint, the Sprint Backlog; instilling quality by adhering to a Definition of Done; and adapting their plan each day toward the Sprint Goal. The Scrum Master is accountable for establishing Scrum as defined in the Scrum Guide, helping everyone understand Scrum theory and practice, and removing impediments to the Scrum Team’s progress.
Therefore, the Developers are not individually accountable for the value of a Product Backlog item selected for the Sprint, but collectively accountable as part of the Scrum Team. The value of a Product Backlog item is determined by the Product Owner, who orders the Product Backlog items based on stakeholder needs and feedback. The Developers collaborate with the Product Owner to understand the value and requirements of each Product Backlog item and deliver a potentially releasable product increment that meets the Definition of Done and the Sprint Goal.
References:
True or False: All planned work for the Product done by the Scrum Team must originate from the Product Backlog.
True
False
References:
Which statement best describes the Sprint Review?
(choose the best answer)
It is a mechanism to control the Developers activities during a Sprint.
It is used to congratulate the Developers if they complete their forecast or to punish
the Developers if they fail to meet their forecast.
It is when the Scrum Team and stakeholders inspect the outcome of a Sprint and
figure out what to do next.
It is a demo at the end of the Sprint for everyone in the organization to check on the
work done.
A sprint review is a collaborative event where the Scrum Team and stakeholders inspect the outcome of a Sprint and determine future adaptations12. It is not a mechanism to control, reward, or punish the Developers, nor is it just a demo of the work done.
True or False: The Product Owner makes sure the Developers select enough from the Product
Backlog for a Sprint to satisfy the stakeholders.
True
False
The Product Owner does not make sure the Developers select enough from the Product Backlog for a Sprint to satisfy the stakeholders. The Developers are the ones who determine how many Product Backlog items they select for a Sprint, based on their capacity and the Sprint Goal1. The Product Owner and the Developers collaborate on the scope of the Sprint during Sprint Planning, but the final decision is up to the Developers2. The Product Owner is accountable for maximizing the value of the product and the work of the Developers, and for managing the Product Backlog[3][3]. The Product Owner does not have the authority to tell the Developers how much work they should do, as this would violate the principle of self-management4.
References:
1: The Scrum Guide, November 2020, p. 6
2: The Scrum Guide, November 2020, p. 10
[3][3]: The Scrum Guide, November 2020, p. 6
4: Understanding and Applying the Scrum Framework, Scrum.org, accessed on December 16, 2023
True or False: A Product Owner with multiple teams working on one product should maintain separate Product Backlogs for each team.
True
False
References:
How much of the Sprint Backlog must be defined during the Sprint Planning event?
(choose the best answer)
Just enough to understand design and architectural implications.
Enough so the Developers can create their forecast of what work they can do.
The entire Sprint Backlog must be identified and estimated by the end of Sprint Planning.
Just enough tasks for the Scrum Master to be confident in the Developers'
understanding of the Sprint.
The amount of the Sprint Backlog that must be defined during the Sprint Planning event is enough so the Developers can create their forecast of what work they can do. This is because:
Other options, such as just enough to understand design and architectural implications, the entire Sprint Backlog being identified and estimated by the end of Sprint Planning, or just enough tasks for the Scrum Master to be confident in the Developers’ understanding of the Sprint, are not valid answers as they do not reflect what must be defined during Sprint Planning or what is required for creating a Sprint forecast.
References:
When is the Sprint Backlog created?
(choose the best answer)
Prior to Sprint Planning.
During refinement.
During the Sprint Retrospective.
During Sprint Planning.
The Sprint Backlog is created during Sprint Planning, where the Developers select the Product Backlog items that they can deliver in the Sprint and create a plan for how to do the work. The Scrum Guide states that "The Sprint Backlog is composed of the Sprint Goal (why), the set of Product Backlog items selected for the Sprint (what), as well as an actionable plan for delivering the Increment (how)."1 The Sprint Backlog is owned and managed by the Developers, who can update it throughout the Sprint as more is learned.
References:
If Product Backlog refinement is needed, when is the ideal time for refinement to take place and
who should participate?
(choose the best two answers)
The Scrum Team during the current Sprint, if they have been unable during
preceding Sprints to define Product Backlog items with enough precision to
begin work.
Business analysts in the organization should do this work for the Scrum Team 1- 2 Sprints ahead of the development Sprints.
The Product Owner must do this as essential work in Sprint O.
The Product Owner takes the time between the end of one Sprint and the start
of the next Sprint to complete refinement.
The Scrum Team on an ongoing basis, defining Product Backlog items into
smaller more precise items that are ready for selection.
The ideal time for refinement to take place and who should participate are the Scrum Team during the current Sprint, if they have been unable during preceding Sprints to define Product Backlog items with enough precision to begin work, and the Scrum Team on an ongoing basis, defining Product Backlog items into smaller more precise items that are ready for selection. This is because:
Other options, such as business analysts doing the refinement work for the Scrum Team, the Product Owner doing the refinement alone in Sprint 0 or between Sprints, or handing off the ownership of the Product Backlog to someone else, are not consistent with the principles and values of Scrum. They may lead to misunderstandings, misalignment, or loss of ownership and accountability.
References:
True or False: During the Sprint Review the stakeholder's role is to reorder the Product Backlog.
True
False
During the Sprint Review, the stakeholder’s role is not to reorder the Product Backlog, but rather to provide feedback and suggestions on the product and the process. Therefore, the answer is false because:
References:
During a Sprint, when is new work or further decomposition of work added to the Sprint
Backlog?
(choose the best answer)
During the Daily Scrum after the Developers approve it.
When the Scrum Master has time to enter it.
When the Product Owner identifies new work.
As soon as possible after it is identified.
New work or further decomposition of work is added to the Sprint Backlog as soon as possible after it is identified because:
References:
Who is accountable for tracking the remaining work toward the Sprint Goal?
(choose the best answer)
The Developers.
The Project Manager.
The Product Owner.
The Scrum Master.
The Developers are the ones who are accountable for tracking the remaining work toward the Sprint Goal. The Developers are self-managing and decide how much work they can do in a Sprint1. They also create and update the Sprint Backlog, which is the plan for how the Developers will achieve the Sprint Goal, and the single source of truth for the work to be done in the Sprint2. The Developers use the Daily Scrum to inspect their progress toward the Sprint Goal and adapt the Sprint Backlog as necessary[3][3]. The Product Owner, the Scrum Master, and the Project Manager (if any) do not have the accountability for tracking the remaining work toward the Sprint Goal, as this is the responsibility of the Developers.
References:
1: The Scrum Guide, November 2020, p. 6
2: The Scrum Guide, November 2020, p. 10
[3][3]: The Scrum Guide, November 2020, p. 11
Which two ways of creating Scrum Teams are consistent with Scrum's values?
(choose the best two answers)
Managers personally re-assign current subordinates to new teams.
The Chief Product Owner determines the new team structures and assignments.
Managers collaborate to assign individuals to specific teams.
Existing teams propose how they would like to go about organizing into the new
structure.
Bring all the people together and let them organize into Scrum Teams.
The Scrum values are commitment, focus, openness, respect, and courage1. These values are embodied by the Scrum Team, which is a self-managing unit that organizes its own work and delivers a valuable product2. The Scrum Team consists of one Scrum Master, one Product Owner, and Developers[3][3]. The best way to create Scrum Teams is to respect the self-management and empowerment of the people who will do the work, and let them decide how to organize themselves into Scrum Teams. This can be done by bringing all the people together and letting them form Scrum Teams based on their skills, interests, and alignment with the product vision4. Alternatively, existing teams can propose how they would like to reorganize themselves into Scrum Teams, based on their feedback and experience5. These ways of creating Scrum Teams are consistent with the Scrum values, as they foster commitment, focus, openness, respect, and courage among the team members and stakeholders. The other options are not consistent with the Scrum values, as they involve managers or the Chief Product Owner imposing their decisions on the team members, which undermines their self-management and empowerment, and creates a lack of trust and collaboration.
References:
1: The Scrum Guide, November 2020, p. 4
2: The Scrum Guide, November 2020, p. 5
[3][3]: The Scrum Guide, November 2020, p. 6
4: Managing Products with Agility, Scrum.org, accessed on December 16, 2023
5: Developing People and Teams, Scrum.org, accessed on December 16, 2023
The Product Owner is the person who will be held accountable if a product does not achieve its
goals or deliver value. Does this mean that the Product Owner has final say over the Definition
of Done?
(choose the best answer)
Yes, the Product Owner decides the Definition of Done. The Developers may be
consulted.
No, the Scrum Team decides the Definition of Done, if it is not a standard of the
organization. The Product Owner is just one member of the Scrum Team.
The Definition of Done is a shared understanding of what it means for work to be complete, and to ensure transparency. The Scrum Guide states that "The Developers are required to conform to the Definition of Done, as defined by the Scrum Team. If there are multiple Scrum Teams working together on a product, they must mutually define and comply with the same Definition of Done."1 This means that the Product Owner does not have the final say over the Definition of Done, but rather collaborates with the Developers and the Scrum Master to agree on the quality standards and expectations for the product.
References:
What is the timebox for the Sprint Review?
(choose the best answer)
2 hours for a one-month Sprint.
1 day.
4 hours for a one-month Sprint.
As long as needed.
The timebox for the Sprint Review is four hours for a one-month Sprint. This is because:
Other options, such as two hours for a one-month Sprint, one day, or as long as needed, are not valid answers as they do not reflect the correct timebox for the Sprint Review.
References:
In accordance with Scrum theory, how should a group of 100 people be divided into multiple
Scrum Teams?
(choose the best answer)
Create a matrix of skills, seniority, and level of experience to assign people to teams.
Check with the allocation department to see who has worked together before and make these the first teams.
Understanding the product, the product vision and the rules of the Scrum framework, the people divide themselves into teams.
It does not really matter since you can rotate the teams every Sprint to spread knowledge.
In accordance with Scrum theory, a group of 100 people should be divided into multiple Scrum Teams by understanding the product, the product vision and the rules of the Scrum framework, and then dividing themselves into teams because:
References:
What are the two responsibilities of testers in a Scrum Team?
(choose the best two answers)
Tracking quality metrics.
Scrum has no "tester" role.
Verifying the work of programmers.
The Developers are responsible for quality.
Finding bugs.
References:
Copyright © 2021-2024 CertsTopics. All Rights Reserved