Winter Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

PSPO-I Scrum Exam Lab Questions

Page: 7 / 13
Total 177 questions

Professional Scrum Product Owner (PSPO I) Exam Questions and Answers

Question 25

The Developers find out during the Sprint that they are not likely to build everything they forecast. What would you expect a Product Owner to do?

(choose the best answer)

Options:

A.

Skip Product Backlog refinement activities.

B.

Inform management that more Developers are needed.

C.

Change the Sprint Goal.

D.

Re-work the selected Product Backlog items with the Developers to meet the Sprint Goal.

E.

Cancel the Sprint.

Question 26

Several Sprints into a project, the Product Owner tells the Scrum Master that a key stakeholder

just started using the product. The stakeholder is unhappy with the quality of the product. What

are two good options for the Scrum Master?

(choose the best two answers)

Options:

A.

Coach the Product Owner on how to talk with the Developers about this

concern.

B.

Wait to bring this up until the Sprint Retrospective.

C.

Explain to the Product Owner that it is up to the Developers to decide on

acceptable quality standards.

D.

Encourage the Product Owner to put quality specifications on the Product

Backlog and express the stakeholder's concern to the Developers.

E.

Bring the concern to the testers to improve how the Product is verified.

Question 27

Which of the following is required by Scrum?

(choose the best answer)

Options:

A.

Sprint Retrospective.

B.

Developers must stand up at the Daily Scrum.

C.

Sprint Burndown Chart.

D.

Release Planning.

E.

All of the above.

Question 28

When should the Product Owner update the project plan?

(choose the best answer)

Options:

A.

Before the Sprint Planning to know how much work will have to be done in the Sprint.

B.

The Product Backlog is the plan in Scrum. It is updated as new information and insights emerge.

C.

After the Daily Scrum to ensure an accurate daily overview of project progress.

D.

The project plan must be updated prior to the Sprint Retrospective.

Page: 7 / 13
Total 177 questions