Professional Scrum Product Owner (PSPO I) Exam Questions and Answers

Question 17

True or False: Multiple Scrum Teams working on the same product or system all select work

from the same Product Backlog.

Options:

A.

True

B.

False

Question 18

Five new Scrum Teams have been created to build one product. A few of the Developers on one of the Scrum Teams ask the Scrum Master how to coordinate their work with the other teams. What should the Scrum Master do?

(choose the best answer)

Options:

A.

Teach them that it is their responsibility to work with the other teams to create anintegrated Increment that is inclusive of all five team ' s work.

B.

Collect the Sprint tasks from the teams at the end of their Sprint Planning and merge that into a consolidated plan for the entire Sprint.

C.

Visit the five teams each day to inspect that their Sprint Backlogs are aligned.

D.

Teach the Product Owner to work with the lead developers on ordering ProductBacklog in a way to avoid too much overlap during a Sprint.

Question 19

What might indicate to a Product Owner that she needs to work more with the Scrum Team?

(choose the best answer)

Options:

A.

The acceptance criteria do not appear to be complete.

B.

She is not working full time with the Scrum team.

C.

People leave the Scrum Team.

D.

The Increment presented at the Sprint Review does not reflect what she thought she had asked for.

Question 20

True or False: Product Owners must specify complete acceptance criteria for a Product

Backlog item before the Developers can select the item in Sprint Planning.

Options:

A.

True

B.

False