Black Friday Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Free and Premium SAP C_TS412_2021 Dumps Questions Answers

SAP Certified Application Associate - SAP S/4HANA Project Systems Questions and Answers

Question 1

Which report can use user-specific layouts?

Options:

A.

Line item report

B.

Enhanced individual overview

C.

Cost element report

D.

Hierarchical report

Buy Now
Question 2

Which sets of dates can be used to schedule networks? Note: There are 2 correct answers to this question

Options:

A.

Basic dates

B.

Forecast dates

C.

Baseline dates

D.

Planned dates

Question 3

Which objects do you have to maintain to enable automatic assignment of material components to the project? Note: There are 2 correct answers to this question

Options:

A.

Material master

B.

Network activity

C.

WBS element

D.

BOM item

Question 4

A service company uses project management and they complain that the system does not prevent

their project managers from exceeding their budgets. What actions do you have to take to solve the problem?

Options:

A.

Activate availability control for the WBS elements. Define the tolerance limits on each WBS element

B.

Activate availability control in the assigned budget profile. Define the tolerance limits in customizing

C.

Activate commitment management in the project definition Enter the budget in the master data of the top WBS element

D.

Activate availability control for projects in the controlling area. Enter the plan data for each WBS element

Question 5

The various work packages in the project are described as individual______________. Choose the correct answer.

Options:

A.

WBS elements

B.

Project definitions

C.

Tasks

D.

Activities

Question 6

Project structure.

You intent to work with predefined project coding mask to create project definitions. What do you have to consider?

Options:

A.

You can create project coding mask X... event if there are project numbers beginning with X.

B.

The standard project definition must differ from the definition of the operative project.

C.

You can use only numbers for a project coding mask definition.

D.

You can use an indicator to determine that only coded project numbers may be used within the project system.

Question 7

You have activated the workflow for confirmation variances in SAP Project System. Who is the receiver of this workflow item?

Options:

A.

The person responsible for the work center

B.

The person responsible for the superior WBS element

C.

The MRP controller for the network

D.

The person responsible for the network activity

Question 8

Which sales documents can update planned revenues on WBS elements? Note: There are 2 correct answers to this question

Options:

A.

Sales order

B.

Billing

C.

Quotation

D.

Inquiry

Question 9

Which of the following data can be maintained in a standard network? Note: There are 3 correct answers to this question

Options:

A.

Document information records

B.

Internally processed activities

C.

Basic dates for activities

D.

Material components

E.

Relationships

Question 10

How are earliest dates and latest dates of activities scheduled?

Options:

A.

Earliest dates are scheduled by backward scheduling, and latest dates by copying the earliest dates

B.

Earliest dates are scheduled by forward scheduling, and latest dates by backward scheduling

C.

Earliest dates and latest dates are scheduled by forward scheduling

D.

Earliest dates are scheduled by backward scheduling, and latest dates by forward scheduling

Question 11

Budgeting is implemented for projects. The budget has been adjusted several times. What standard report type provides an overview of adjustments on the budget?

Options:

A.

Structure overview for budgets

B.

Hierarchical report on budget updates

C.

Cost element report on budget updates

D.

Line item report for budgets

Question 12

You want to allocate overhead rates to a WBS element. What must you assign to the WBS element?

Options:

A.

Settlement rule

B.

Investment profile

C.

Results analysis key

D.

Costing sheet

Question 13

Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20. The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day. What do you recommend to set up the requirement date for the component ?

Options:

A.

Set up the requirement date aligned with the activity finish date and an offset of 15 days.

B.

Set up the requirement date manually as February 5.

C.

Set up the requirement date aligned with the activity start date and an offset of 5 days

D.

Set up the requirement date aligned with the activity start date and a negative offset of 5 days

Question 14

Resources

How can you define external task in your project.

Note : there are 2 correct answers for this question.

Options:

A.

Assign a purchase order for external processing to the project definition.

B.

Create an external activity in a network.

C.

Create a service milestone.

D.

Create a service activity in a network.

Question 15

Dates

How are earliest dates and latest dates of activities schedule?

Options:

A.

Earliest dates are scheduled by backward scheduling, and the latest dates by forward scheduling.

B.

Earliest dates are scheduled by forward scheduling , and the latest dates by backward scheduling.

C.

Earliest dates and latest dates are scheduled by forward scheduling.

D.

Earliest dates are scheduled by backward scheduling, and the lates dates by copying the earliest dates.

Question 16

You have a project with a network, material and milestone. You want to plan an activity to start two days after its predecessor. How can you do that?

Note : there are 2 correct answers for this question.

Options:

A.

Use an offset of two days for the relationship of both activities.

B.

Use an offset of two days for milestone date.

C.

Use an offset of two days for the requirement date of the material component

D.

Calculate the start date of the activity and set the constraint "Must start on" accordingly.