Black Friday Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

SAP SAP Certified Application Associate C_TS412_2021 New Questions

SAP Certified Application Associate - SAP S/4HANA Project Systems Questions and Answers

Question 13

Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20. The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day. What do you recommend to set up the requirement date for the component ?

Options:

A.

Set up the requirement date aligned with the activity finish date and an offset of 15 days.

B.

Set up the requirement date manually as February 5.

C.

Set up the requirement date aligned with the activity start date and an offset of 5 days

D.

Set up the requirement date aligned with the activity start date and a negative offset of 5 days

Question 14

Resources

How can you define external task in your project.

Note : there are 2 correct answers for this question.

Options:

A.

Assign a purchase order for external processing to the project definition.

B.

Create an external activity in a network.

C.

Create a service milestone.

D.

Create a service activity in a network.

Question 15

Dates

How are earliest dates and latest dates of activities schedule?

Options:

A.

Earliest dates are scheduled by backward scheduling, and the latest dates by forward scheduling.

B.

Earliest dates are scheduled by forward scheduling , and the latest dates by backward scheduling.

C.

Earliest dates and latest dates are scheduled by forward scheduling.

D.

Earliest dates are scheduled by backward scheduling, and the lates dates by copying the earliest dates.

Question 16

You have a project with a network, material and milestone. You want to plan an activity to start two days after its predecessor. How can you do that?

Note : there are 2 correct answers for this question.

Options:

A.

Use an offset of two days for the relationship of both activities.

B.

Use an offset of two days for milestone date.

C.

Use an offset of two days for the requirement date of the material component

D.

Calculate the start date of the activity and set the constraint "Must start on" accordingly.