SIAM Professional SIAMP Full Course Free

Page: 2 / 4
Total 56 questions

EXIN SIAM Professional Exam Questions and Answers

Question 5

ZYX completed the Discovery and Strategy stage one week ago. The Plan and Build stage is expected to take six months to complete. ZYX would like to put a service integrator in place before they complete the design of the detailed SIAM model

The outline SIAM model proposed that ZYXS would be an internal service integrator because of their service integration capabilities Additional staff would be recruited to provide additional capacity. The development and support staff from ZYXS would be transferred to ZYXD to become an internal service provider.

The CEO does not want to use a hybrid or lead supplier structure Because of the internal capabilities of ZYXS, no evaluation has been done for using an external service integrator

The ZYXS IT Director has just announced that she. and all ten staff identified to work as the service integrator, are leaving ZYXS in four weeks They intend to form their own company ZSSIAM, specializing in providing service integration services

OUTSCO is a global provider of a range of outsourced services They are in the last year of a 10-year contract to provide services to ZYXUK Over the last 2 years their performance has decreased OUTSCO can also provide service integration services They have a good reputation as a flexible and reliable service integrator who are willing to amend their SIAM model.

SIAMRUS is a global provider of service integration services in the manufacturing sector Their SIAM model includes a standardized process model, with every provider using the same process, a shared toolset owned by SIAMRUS, and 5 contracted service providers They recently provided an outline SIAM strategy for ZYXUK

What is the best approach for ZYX to appoint a service integrator?

Options:

A.

Appoint SIAMRUS as the service integrator for ZYX without further analysis

B.

O Appoint ZSSIAM as the service integrator for ZYX without further analysis

C.

O invite OUTSCO, SIAMRUS and ZSSIAM to bid to be the service integrator

D.

Update the current contract with OUTSCO to include service integration

Question 6

The CIO is about to establish a project to transition ZYX to a SIAM operating model.

Which are the most important governance requirements to initially focus on, given the situation of ZYX?

Options:

A.

At this point in planning the transition project, the most important area for the CIO to focus on is strategic planning This includes building the SIAM business case reviewing legal requirements, identifying strategic nsks and ensuring a robust control structure is in place

B.

Before initiating the transition project designing and completing a detailed tooling strategy is critical for ZYX. This will help ZYX to select the service integrator and the service providers and will ensure a smooth onboarding of service providers into the integrated solution

C.

in order to ensure a smooth transition to the SIAM operating model, the CIO must focus on mitigating risks such as the ownership of tools, processes and data This is in order to prevent any loss of knowledge and skills as service providers are replaced

D.

The first task for the CIO is to establish governance over service levels and key performance indicators This will ensure that all contracts and agreements with SIAMRUS and the service providers are in place before transitioning to the SIAM operating model

Question 7

The CEO of ZYX has commissioned SIAMRUS to assess the readiness of ZYX to adopt SIAM. She knows that in order to get approval for the SIAM business case from the Board of Directors, she will have to be able to demonstrate that SIAM will make a significant contribution to the corporate strategic objectives. There is no appetite from the Board for ZYX to use any ZYX staff to provide the service integration capability

Which ZYX strategic objective can SIAM contribute to most for ZYX?

Options:

A.

Control headcount

B.

Ensure delivery against contracts

C.

invest in their people

D.

Retain existing business

Question 8

ZYX have decided to use the external service integrator structure The ZYX CEO wants to minimize risks to service availability. In order to avoid reliance on single service providers the CEO wants to use four different providers for hosting There will be one service provider for hosting for each of the following countries

-the UK

-Germany

-the Netherlands

- Australia

To provide resilience every application used by ZYX will be hosted by three different hosting service providers

The CEO wants to ensure a rapid introduction of new services and service providers She also wants to ensure that the costs for the service integrator are as low as possible The ZYXH legal team does not want to make the drafting of the contracts more difficult than necessary

It is clear that there is a single structure needed for the service integrator contract

Which contract structure is the most appropriate for ZYX?

Options:

A.

Adopt that same structure for the hosting provider contracts

B.

Adopt a single structure for the hosting provider contracts

C.

Adopt custom structures for each hosting provider contract

D.

Ask the hosting providers to provide their own structure.

Page: 2 / 4