New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Free and Premium Exin SIAMP Dumps Questions Answers

Page: 1 / 4
Total 56 questions

EXIN SIAM Professional Exam Questions and Answers

Question 1

The SIAM model in ZYX has been successfully implemented and operational for 6 months All service providers have signed up to multi-party service level agreements and a detailed collaboration agreement. All providers are either using or interfacing with the common ITSM tool.

NETSCO is providing all LAN and WAN services across the group Although NETSCO is consistently achieving all of its service levels and attends all necessary meetings. NETSCO is not contributing to the overall relationship with the other service providers.

The service integrator wishes to address this problem with NETSCO

What action should the service integrator take?

Options:

A.

Do nothing immediately as it is still early in the contract but monitor the contributions from NETSCO.

B.

Hold a meeting with NETSCO to discuss why they are not engaging in the cultural elements of the contract

C.

Reinforce the need for positive cultural engagement from all service providers at the next service provider forum.

D.

There is nothing that the service integrator can do as NETSCO is meeting all of the contracted service levels .

Buy Now
Question 2

A consequence of ZYX’s SIAM transition is that the small IT team of 5 staff within ZYXUK, who currently develop and support small stand-alone applications, are being displaced, with their roles outsourced to a new external service provider. This external service provider will provide a standardized approach to the development and B support of bespoke applications across all of the ZYX organizations It is hoped that this will allow similar requirements from different ZYX organizations to be identified a more manner

The impacted staff is expected to be reluctant to transfer to the new service provider, who is based outside of the UK and has a very different organizational culture B I he project team is concerned that these staff members may either be reluctant to pass on their knowledge of the existing applications, or may leave before knowledge transfer can take place

What would be the most effective strategy for handling this risk?

Options:

A.

identify the one or two key members of the team, who have the greatest knowledge of the applications Find these individuals suitable alternative roles within the retained IT capability, to ensure that the knowledge does not leave the organization

B.

identify a minimum set of documentation. Task the impact team to produce or update these documents for each application. Put in place a handover process which includes formal review and sign-off of the documents by the new service provider

C.

Provide clear communication to the impacted staff regarding why the change is happening, the implications for themselves and the timescales involved. Incentivize some or all of the impacted staff to remain throughout the handover and early life support phases.

D.

Take immediate steps to embed staff from the new service provider, to work alongside the impacted staff members Initiate a coordinated exercise to ensure that all existing documentationregarding the applications is brought up to date.

Question 3

The CEO has asked the IT Director to create a SIAM strategy for ZYX that aligns with the mandate for change and the corporate strategy The CEO wants it as soon as possible.

What should the IT Director do?

Options:

A.

Adopt the SIAM strategy proposed by SIAMRUS for ZYX

B.

Adopt the SIAM strategy proposed by SIAMRUS for ZYXUK

C.

Design a new SIAM strategy ignoring the report from SIAMRUS

D.

Design a new SIAM strategy using the report from SIAMRUS as input

Question 4

ZYX has implemented a SIAM structure, appointing SIAMRUS as the service integrator.

The SIAM strategy is to consolidate to a smaller number of service providers over time as existing contracts expire Until then. ZYX wants all current service providers to be part of the SIAM ecosystem.

What should ZYX do?

Options:

A.

Communicate the SIAM strategy and instruct SIAMRUS to speak to all service providers to explain their role

B.

Draw up a collaboration agreement across all service providers setting out how they will work together

C.

Put a clause in service provider contracts that SIAMRUS is acting on behalf of ZYX or negotiate themselves

D.

Write to all the service providers informing them that SIAMRUS has been appointed as the service integrator

Question 5

ZYX completed the Discovery and Strategy stage one week ago. The Plan and Build stage is expected to take six months to complete. ZYX would like to put a service integrator in place before they complete the design of the detailed SIAM model

The outline SIAM model proposed that ZYXS would be an internal service integrator because of their service integration capabilities Additional staff would be recruited to provide additional capacity. The development and support staff from ZYXS would be transferred to ZYXD to become an internal service provider.

The CEO does not want to use a hybrid or lead supplier structure Because of the internal capabilities of ZYXS, no evaluation has been done for using an external service integrator

The ZYXS IT Director has just announced that she. and all ten staff identified to work as the service integrator, are leaving ZYXS in four weeks They intend to form their own company ZSSIAM, specializing in providing service integration services

OUTSCO is a global provider of a range of outsourced services They are in the last year of a 10-year contract to provide services to ZYXUK Over the last 2 years their performance has decreased OUTSCO can also provide service integration services They have a good reputation as a flexible and reliable service integrator who are willing to amend their SIAM model.

SIAMRUS is a global provider of service integration services in the manufacturing sector Their SIAM model includes a standardized process model, with every provider using the same process, a shared toolset owned by SIAMRUS, and 5 contracted service providers They recently provided an outline SIAM strategy for ZYXUK

What is the best approach for ZYX to appoint a service integrator?

Options:

A.

Appoint SIAMRUS as the service integrator for ZYX without further analysis

B.

O Appoint ZSSIAM as the service integrator for ZYX without further analysis

C.

O invite OUTSCO, SIAMRUS and ZSSIAM to bid to be the service integrator

D.

Update the current contract with OUTSCO to include service integration

Question 6

The CIO is about to establish a project to transition ZYX to a SIAM operating model.

Which are the most important governance requirements to initially focus on, given the situation of ZYX?

Options:

A.

At this point in planning the transition project, the most important area for the CIO to focus on is strategic planning This includes building the SIAM business case reviewing legal requirements, identifying strategic nsks and ensuring a robust control structure is in place

B.

Before initiating the transition project designing and completing a detailed tooling strategy is critical for ZYX. This will help ZYX to select the service integrator and the service providers and will ensure a smooth onboarding of service providers into the integrated solution

C.

in order to ensure a smooth transition to the SIAM operating model, the CIO must focus on mitigating risks such as the ownership of tools, processes and data This is in order to prevent any loss of knowledge and skills as service providers are replaced

D.

The first task for the CIO is to establish governance over service levels and key performance indicators This will ensure that all contracts and agreements with SIAMRUS and the service providers are in place before transitioning to the SIAM operating model

Question 7

The CEO of ZYX has commissioned SIAMRUS to assess the readiness of ZYX to adopt SIAM. She knows that in order to get approval for the SIAM business case from the Board of Directors, she will have to be able to demonstrate that SIAM will make a significant contribution to the corporate strategic objectives. There is no appetite from the Board for ZYX to use any ZYX staff to provide the service integration capability

Which ZYX strategic objective can SIAM contribute to most for ZYX?

Options:

A.

Control headcount

B.

Ensure delivery against contracts

C.

invest in their people

D.

Retain existing business

Question 8

ZYX have decided to use the external service integrator structure The ZYX CEO wants to minimize risks to service availability. In order to avoid reliance on single service providers the CEO wants to use four different providers for hosting There will be one service provider for hosting for each of the following countries

-the UK

-Germany

-the Netherlands

- Australia

To provide resilience every application used by ZYX will be hosted by three different hosting service providers

The CEO wants to ensure a rapid introduction of new services and service providers She also wants to ensure that the costs for the service integrator are as low as possible The ZYXH legal team does not want to make the drafting of the contracts more difficult than necessary

It is clear that there is a single structure needed for the service integrator contract

Which contract structure is the most appropriate for ZYX?

Options:

A.

Adopt that same structure for the hosting provider contracts

B.

Adopt a single structure for the hosting provider contracts

C.

Adopt custom structures for each hosting provider contract

D.

Ask the hosting providers to provide their own structure.

Question 9

Project NEWGEN was completed against demanding timescales Because of time pressures, ZYX reduced the scope for testing of the end-to-end processes.

-SIAMRUS is the service integrator and also provider of the service desk for the SIAM ecosystem

-ZYXS is the internal service provider for NEWBNK, which is hosted by OUTSCO

-NETSCO provides the wide area network connecting the OUTSCO data center to the banks using NEWBNK.

Since the transition to SIAM, users of NEWBNK have experienced a significant increase in the time taken to fix incidents The ZYX sales team is now experiencing resistance from customers who were expected to migrate to NEWBNK This is affecting the planned rollout of the new application The ZYX sales team has told the customers that the issues were caused by the providers to ZYX not working together, and not the NEWBNK application itself.

What is the best approach for SIAMRUS to improve the situation?

Options:

A.

Design and implement a program of organizational change management and skills training with each service provider and measure the success of it

B.

Implement a new customer marketing campaign focusing on the benefits of NEWBNK and stress that the issues are temporary and will be resolved M|

C.

Implement Lean systems thinking in each provider to review and optimize the procedures, eliminating waste within the internal activities of the providers

D.

Use the process forums to mao analyze and improve the end to end processes assigning specific activities to appropriate mdividuals

Question 10

The SIAM strategy for ZYX has been agreed:

-There will be a mix of new service providers and continuing existing service providers

-An external service integrator will be appointed

-ZYXS will provide the service desk.

-An agreement has been reached with OUTSCO to extend their contract to provide services to ZYXUK by two years

As key activities for the critical path to implement the SIAM model for ZYX, three parties must be transitioned into the SIAM model (listed in random order):

-continuing service providers

-the service integrator

-new service providers

In this instance, which sequence of activities offers the least risk to continuity of service for all ZYX companies'?

Options:

A.

All parties at the same time

B.

First the continuing service providers, then the service integrator and the new service providers last

C.

First the service integrator, then the new service provider, and the continuing service providers last

D.

First the service integrator, then both continuing and new service providers at the same time

Question 11

Project NEWGEN is in the Discovery and Strategy stage. SIAMRUS is assisting ZYX with the design of the SIAM model ZYX has decided to use OUTSCO as an external service integrator but they have not yet been appointed.

The CIO is concerned that the retained capabilities might not have the necessary capability to perform their new role in the SIAM model

What is the best course of action?

Options:

A.

Ask the service integrator after they are appointed to create customized role profiles.

B.

Ask staff to apply for a new role with the service integrator in the new SIAM ecosystem

C.

Create a framework for generic role profiles for the retained capabilities

D.

-Ask staff to apply for a new role with the service providers in the new SIAM ecosystem O . Create customized role profiles for all parties in the new SIAM ecosystem

E.

Determine which staff has the right capabilities for their new role

F.

. Have the staff do assessments based on generic role profiles from a framework - Fire those staff from the original organization that are lacking SIAM skills

Question 12

ZYX has appointed SIAMRUS and the service management staff from ZYXS as a hybrid service integrator They will use the SIAM model from SIAMRUS

The IT staff from ZYXS and ZYXUK will form a new internal service provider. ZYXSAPP. ZYXSAPP will provide the services for application development and application support

ZYXH will provide the retained capabilities The contract with OUTSCO will not bo renewed ZYX wants to start planning the implementation of the SIAM model

What should SIAMRUS do that would most support ZYX?

Options:

A.

Lead the commercial discussions with new and legacy providers

B.

Review the exit management requirements in the contract with OUTSCO

C.

Start the activities to transition ZYXSAPP into the SIAM model

D.

Take on the accountability for deciding on the implementation approach

Question 13

ZYX has decided on their SIAM strategy and appointed SIAMRUS as the service integrator.

The decision has been made to consolidate services into four service groups (in order of proportion of the services)

-OUTSCO: service desk, desktop and laptop support services, networking, infrastructure support

-ZYXS bespoke application support and development

-ZYXD data centers and hosting

-BANKSCO: BCT and BNK application support

Services from all other current service providers will be transitioned into these service groups as their contracts expire

After the service integrator has been onboarded, which of the providers should be onboarded as the first priority?

Options:

A.

O BANKSCO

B.

O OUTSCO

C.

O ZYXD

D.

ZYXS

Question 14

The ZYX Board of Directors decided that the proposal from SIAMRUS for ZYXUK was not suitable to be used for the whole of the group, and asked the ZYXS IT Director to lead the creation of a new SIAM strategy. This new SIAM strategy has now been approved by the NEWGEN Executive Steering Board.

What is the best approach to ensure that the ZYXUK Management Board supports the implementation of this SIAM Strategy?

Options:

A.

Delay the implementation of the strategy until the ZYXUK Management Board has formally approved it

B.

Ensure that each ZYXUK Management Board member is teamed with a member of the strategy team they know

C.

Ensure that the ZYXUK stakeholders understand how their perspective has been considered within the strategy

D.

Provide financial incentives to buy into the strategy for ZYXUK stakeholders who are not yet convinced

Question 15

What best describes ZYX's strategic drivers for transitioning to a SIAM model?

Options:

A.

To enable the design implementation operation and improvement of integrated end-to-end services

•To ensure that these services are aligned with the ZYX corporate objectives, and allow problematic legacy systems to be retired

B.

To reduce the overhead and cost of managing an increasing number of service providers across the different ZYX companies

-To reduce the incidence of contract overlap, where more than one provider is being paid to deliver the same service within ZYX

C.

To reduce the risk of the service providers operating in silos, focused on their own targets rather than the wider end-to-end service

-To promote collaboration between providers in seeking ways to reduce IT operating costs and enable Agile development of new services C .

D.

To reduce the costs of operating IT. while at the same time ensuring that agreed service levels are met

-To enable IT capabilities that support agility and rapid expansion of the ZYX business into new geographical areas

Question 16

There are many factors that can influence the design of a SIAM model

Which factor will most influence the choice of the SIAM structure for ZYX?

Options:

A.

Capabilities of the staff working in the ZYX organizations

B.

Multiple geographical locations of ZYX companies

C.

The report and proposed SIAM strategy from SIAMRUS

D.

Willingness of service providers to be part of the SIAM model

Page: 1 / 4
Total 56 questions