Selected AgilePM-Foundation AgilePM Questions Answers

Agile Project Management (AgilePM) Foundation Exam Questions and Answers

Question 25

How is contingency typically managed in a DSDM project?

Options:

A.

Not needed in a DSDM project.

B.

Allowed adding a percentage to the high-level estimates.

C.

Managed by varying the features to be delivered.

D.

Managed by varying time and cost

Question 26

Which purpose relates to the Consolidation in a structured Timebox?

Options:

A.

To confirm the detail of all the requirements to be delivered by the structured Timebox.

B.

To address the requirements and test the structure Timebox product.

C.

To formality accept the structured Timebox deliverables.

D.

To tie up any loose ends related to Evolutionary Development

Question 27

Which of the following statements about positive characteristics of an effective change team (Lencioni) are true?

    Members should be encouraged to draw attention to colleagues' failures to meet commitments.

    Conflict should be avoided to maintain good relationships.

Options:

A.

Only 1 is true.

B.

Only 2 is true.

C.

Both 1 and 2 are true.

D.

Neither 1 nor 2 is true.

Question 28

What DSDM Principles requires the transparency of all work being performed by the team?

Options:

A.

Principle 1- Focus on the Business Need

B.

Principle 1 – Build incrementally from Firm Foundations

C.

Principle 66-Develop iteratively

D.

Principle 8-Demonstrate Control