Question 21

According to Pink, which three factors are key motivators for 'knowledge work'?

Options:

A.

Dissatisfiers, rewards, and safety.

B.

Autonomy, safety, and self-esteem.

C.

Hygiene factors, autonomy, and self-actualization.

D.

Autonomy, mastery, and purpose.

Question 22

What is the purpose of the Foundations Summary?

Options:

A.

To document how stakeholders will be engaged and standards that will be applied.

B.

To define the tools, techniques, customer, practices and standards that will be applied

C.

To provide enough information to decide whether the project is likely to deliver return on investment

D.

To define the scope of the requirements that the project needs to address

Question 23

According to the 'change formula' (Beckhard and Harris), which response will increase an individual's 'dissatisfaction with the status quo'?

Options:

A.

Amend performance targets during the change.

B.

Communicate the danger of inaction.

C.

Clarify the steps users need to take.

D.

Focus on the benefits of the change.

Question 24

During what phase should a baseline of the Evolving Solution be put into operational use?

Options:

A.

Foundations

B.

Evolutionary Development

C.

Deployment

D.

Post-Project