PSM-I Premium Exam Questions

Page: 12 / 20
Total 268 questions

Professional Scrum Master I Questions and Answers

Question 45

Which does a self-organizing Development Team choose?

Options:

A.

Sprint length.

B.

How to best accomplish its work.

C.

Stakeholders for the Sprint Review.

D.

When to release, based on its progress.

E.

Product Backlog ordering.

Question 46

Which three questions might be answered by Development Team members at the Daily Scrum? (Choose three.)

Options:

A.

How is the Sprint proceeding?

B.

What did I do yesterday that helped the Development Team meet the Sprint Goal?

C.

Why were you late?

D.

What will I do today to help the Development Team meet the Sprint Goal?

E.

How many hours did I spend on the project yesterday?

F.

What will I be working on tomorrow?

G.

Do I see any impediment that prevents me or the Development Team from meeting the Sprint Goal?

Question 47

Marian is the Product Owner envisioning a project for a new release of her product. She made a projection of a release date based upon a sustained velocity of 17 completed units of work per Sprint. Over the first 3 Sprints, the average velocity was 13 for work that the Development Team estimated as 90% done. The Development Teams, feeling the need to meet the plan, figured that a velocity of 17 was within their reach.

A good way to continue is:

Options:

A.

The Development Team makes sure that all of the selected scope per Sprint is as “Done” as possible. The undone work is estimated and added to the Sprint Backlog of the next Sprint, so it doesn’t mess up the Product Backlog.

B.

Add enough people to the Development Team for the deadline to be made.

C.

The opportunity to inspect and adapt is lost. Opaqueness has replaced transparency. Predictability has dropped below zero. The produced software is not usable. As the rules of Scrum have not been respected, it is the Scrum Master’s duty to assess whether repair is possible, or a restart with a more reliable team. If not, the Scrum Master should cancel the project.

D.

The Development Team should remind Marian to find funding for enough Release Sprints in which the remaining work can be done.

Question 48

Which two activities will a Product Owner engage in during a Sprint? (Choose two.)

Options:

A.

Run the Daily Scrum.

B.

Prioritize the Development Team’s work on the Sprint Backlog.

C.

Update the Sprint burndown chart.

D.

Answer questions from the Development Team about items in the current Sprint.

E.

Work with the stakeholders.