Immediately after the conclusion of the previous Sprint.
C.
The Monday following the Sprint Review.
D.
Immediately following the next Sprint Planning.
Answer:
B
Explanation:
Explanation:
The next Sprint begins immediately after the conclusion of the previous Sprint, as stated in the Scrum Guide: “Sprints have consistent durations throughout a development effort. A new Sprint starts immediately after the conclusion of the previous Sprint.”
Question 26
What is the typical size for a Scrum Team?
(choose the best answer)
Options:
A.
7 plus or minus 3.
B.
At least 7.
C.
9
D.
10 or fewer.
Answer:
D
Explanation:
Explanation:
The correct answer is D. 10 or fewer. According to the Scrum Guide 20201, “The Scrum Team is small enough to remain nimble and large enough to complete significant work within a Sprint, typically 10 or fewer people.” The other options are outdated or incorrect. Option A was based on the previous version of the Scrum Guide, which suggested a range of 3 to 9 developers2. Option B is too vague and does not account for the upper limit of team size. Option C is too specific and does not allow for flexibility.
Question 27
When might a Sprint be abnormally cancelled?
Options:
A.
When the Development Team feels that the work is too hard.
B.
When the Sprint Goal becomes obsolete.
C.
When the sales department has an important new opportunity.
D.
When it becomes clear that not everything will be finished by the end of the Sprint.
Answer:
B
Explanation:
Explanation:
According to the Scrum Guide1, a Sprint can be cancelled before the Sprint time-box is over. Only the Product Owner has the authority to cancel the Sprint, although he or she may do so under influence from the stakeholders, the Developers, or the Scrum Master. A Sprint would be cancelled if the Sprint Goal becomes obsolete. This might occur if the company changes direction or if market or technology conditions change. In general, a Sprint should be cancelled if it no longer makes sense given the circumstances. But, due to the short duration of Sprints, cancellation rarely makes sense.
References: Scrum Guide
Question 28
Which are properties of the Daily Scrum? (Choose two.)
Options:
A.
It is facilitated by the team lead.
B.
It is held first thing in the morning.
C.
It is fifteen minutes or less in duration.
D.
It is free from and designed to promote conversation.
E.
It consists of the Scrum Master asking the Team members the three questions.
F.
Its location and time remain constant.
Answer:
C, F
Explanation:
Explanation:
According to the Scrum Guide1, each event in Scrum is a formal opportunity to inspect and adapt something. These events are specifically designed to enable critical transparency and inspection. Failure to include any of these events results in reduced transparency and is a lost opportunity to inspect and adapt. All events are time-boxed events, such that every event has a maximum duration. Once a Sprint begins, its duration is fixed and cannot be shortened or lengthened. The remaining events may end whenever the purpose of the event is achieved, ensuring an appropriate amount of time is spent without allowing waste in the process. The time-box for the Daily Scrum is 15 minutes or less for a one-month Sprint. Its location and time remain constant.