Oracle Project Management Cloud 2024 Implementation Professional Questions and Answers

Question 25

Your customer has different accounting and project accounting periods, and sometimes enters invoices with an invoice date in the open project accounting and closed accounting periods. Which two statements are true about how project accounting and accounting dates will be populated in such invoices? (Choose two.)

Options:

A.

Accounting date is the same as the original invoice date.

B.

Project accounting date is the same as the original invoice date.

C.

Project accounting date is the first day of the first open project accounting period.

D.

Project accounting date is the last day of the open project accounting period.

E.

Accounting date is the first day of the first open accounting period.

Question 26

Your customer wants to perform billing based on the Percent Spent invoice method. Identify two setups that are required in project contracts for calculating invoice amounts as per their requirement. (Choose two.)

Options:

A.

billing events

B.

bill plan

C.

expenditure items

D.

billing controls

E.

invoice method

Question 27

You have a billable project for which the following details are provided:

Associated Inception-To-Date (ITD) Project Actual Cost: USD 60

Associated Project Budgeted Cost: USD 300

Contract Amount: USD 1000

Project Funded Amount: USD 750

Sum of Existing Revenue Events: USD 80

Identify the Associated Project Spent revenue that will get generated based on the preceding details. (Choose the best answer.)

Options:

A.

USD 184

B.

USD 120

C.

USD 134

D.

USD 70

Question 28

Your company uses an accounting calendar with periods that are identical to calendar months. A contract resource has been identified to work for six months on an accounting close cycle project. The resource is planned to start with 10 days left in the first period and to end 20 days into the last period. For the remaining periods, the resource must be loaded on all working days of the month. You are required to distribute the budget, forecast, and planning amounts across periods based on the task duration.

Which predefined spread curve must be used to meet this requirement? (Choose the best answer.)

Options:

A.

Daily Spread Basis

B.

Back Loaded

C.

Bell Curve

D.

S-Curve

E.

Even