Question 17

You are managing a project based on a Waterfall model. You define a project and a project plan in Oracle Project Management with tasks and subtasks applicable to each of the phases of the project: Initiation, Discovery, Design, Build, Test, and Deploy. As a project manager, you want to define deliverables for your project requirements that are elucidated during the Discovery phase of your project. You now want to understand how the inheritance between requirements, tasks, and deliverables works.

Which two are correct statements in this scenario? (Choose two.)

Options:

A.

The association of a deliverable with a task is dependent on associating a requirement with a task.

B.

You associate a deliverable with a task independent of associating a requirement with a task.

C.

A deliverable associated with a requirement is automatically associated with the tasks created for that requirement.

D.

A deliverable associated with a requirement is not automatically associated with the tasks created for that requirement.

Question 18

Your customer has a requirement to import and process third-party transactions that are “costed” and “accounted”.

Which configuration option needs to be set satisfy the requirement? (Choose the best answer.)

Options:

A.

Import Options

B.

Document Options

C.

Transaction Source Options

D.

Document Entry Options

Question 19

When scheduling the Update Project Performance Data process to run on a periodic basis, which summarization method would you select? (Choose the best answer.)

Options:

A.

Bulk

B.

Detail

C.

Incremental

D.

Summary

Question 20

Your client organization has recently undergone a restructuring exercise that has resulted in the creation of new jobs. The Resource Breakdown Structure (RBS) was previously created with existing jobs, and now the new jobs have been added to the existing Resource Breakdown Structure.

Identify the correct statement about the RBS and new resources. (Choose the best answer.)

Options:

A.

If the “Allow resource changes at project level” option is set to No, the new resources and resource formats that are added to a Planning Resource Breakdown Structure for one project are not available for other projects.

B.

If the “Allow resource changes at project level” option is set toNofor the RBS, then the resources added to the Planning Resource Breakdown Structure are automatically available for use on the projects.

C.

If the “Allow resource changes at project level” option is set to Yes for the RBS, the new resources are available automatically at project level.

D.

If the “Allow resource changes at project level” option is enabled for the RBS, the new resources added at project level are automatically reflected in the RBS.