Winter Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

Last Attempt SPS Questions

Page: 2 / 3
Total 40 questions

Scaled Professional Scrum (SPS) Exam Questions and Answers

Question 5

If two Scrum Teams are added to a product that previously had only one Scrum Team, what will

be the immediate impact on the productivity of the original Scrum Team?

(choose the best answer)

Options:

A.

Its productivity is likely to stay the same.

B.

Its productivity is likely to decrease.

C.

Its productivity is likely to increase.

Question 6

How should multiple Scrum Teams deliver a valuable and useful Increment in a Sprint?

(choose the best answer)

Options:

A.

Each Scrum Team delivers done Increments of its own area of responsibility. These

Increments are integrated into a whole product during stabilization prior to release.

B.

Each Scrum Team provides a unique done Increment that includes the team's added

functionality.

C.

Each Sprint, all Scrum Teams complete work that integrates with all of the other work

from other Scrum Teams on the initiative.

D.

Functionality not integrated with the work of other Scrum Teams may be delivered as

unintegrated Increments to demonstrate the value created by the Scrum Teams

unable to completely integrate their Increments.

Question 7

Scenario B: Six Team Nexus with complex dependencies

A six team Nexus is developing a complex product, with different parts of the product that only

certain Scrum Teams can work on. In fact, there are some highly specialized individuals outside

the Nexus that are required for some of the work. In past Sprints the Nexus encountered

challenges dealing with the many dependencies between Scrum Teams.

Some individual Scrum Teams in this Nexus have said that they do not see how the work they

are doing is contributing to the product's progress. What is the best remedy for this situation?

(choose the best answer)

Options:

A.

During Nexus Sprint Planning, have all the teams plan the Sprint together in one

room, so they can see what other teams are working on.

B.

During Nexus Sprint Planning, ensure that all Scrum Teams understand the Nexus

Sprint Goal.

C.

Ask the Scrum Master to explain to the teams that the Product Owner can choose

which features to work on, as she has the final say.

D.

During Nexus Sprint Planning, ask each Scrum Team to create a Sprint Goal that

describes the purpose of the Sprint.

Question 8

From the list below, what is the most important concern for multiple Scrum Teams when they

are working from the same Product Backlog?

(choose the best answer)

Options:

A.

Meeting original scope projections.

B.

Minimizing dependencies between teams.

C.

Clear definition of requirements.

D.

Making sure there is enough work for everyone on every team.

Page: 2 / 3
Total 40 questions