Winter Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

Helping Hand Questions for H12-425

Page: 9 / 9
Total 240 questions

HCIP-Data Center Facility Deployment Questions and Answers

Question 33

DuringNetCol5000-C commissioning, the opening of the water valve needs to be adjusted to minimum when you inject water and exhaust air.

Options:

A.

TRUE

B.

FALSE

Question 34

ECC800 does not support wireless communications.

Options:

A.

TRUE

B.

FALSE C.

C.

Question 35

The compressor suction pressure of NetCol5000-A25kW is low. It is possible that ().

Options:

A.

The electric heater is burnt out

B.

The refrigerant is insufficient.

C.

There is water vapor in the pipe

D.

The condensing pressure is low.

Question 36

( ) can connect to the AI/DI port on the access actuator.

Options:

A.

IC card reader

B.

Fingerprint and card reader

C.

Exit button

D.

Magnetic

Page: 9 / 9
Total 240 questions