Winter Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

Note! Following H12-425 Exam is Retired now. Please select the alternative replacement for your Exam Certification. The new exam code is H12-425_V2.0

Verified By IT Certified Experts

CertsTopics.com Certified Safe Files

Up-To-Date Exam Study Material

99.5% High Success Pass Rate

100% Accurate Answers

Instant Downloads

Exam Questions And Answers PDF

Try Demo Before You Buy

Certification Exams with Helpful Questions And Answers

HCIP-Data Center Facility Deployment Questions and Answers

Question 1

The humidifier that used in NetCol8000-A is ().

Options:

A.

Electrode humidifier

B.

Infrared humidifier

C.

Wet film humidifier

D.

High-pressure micro-mist humidifier

Buy Now
Question 2

When installing the power line on the UPS5000-E, if there are different sources on the main-lines and bypass, you need to remove the copper bars connected to the bypass and main lines first, and then connect the main circuit and bypass input respectively.

Options:

A.

TRUE

B.

FALSE

Question 3

Power segment function is enabled on UPS2000-G-20kVA. Which will cause the loads connected with PL terminals power- off?

Options:

A.

Overload

B.

Battery under voltage

C.

Mains input interruption

D.

Mains Under voltage