BICSI Registered Communications Distribution Designer – RCDDv14 Questions and Answers

Question 5

The ICT distribution designer is hired to design a Telecommunications Room on the third floor of a building. The size of the floor is 20 m by 26 m (92 x 85 It). What is to be the MINIMUM size of the TR?

Options:

A.

Shallow Room, no minimum room size

B.

=3 m (10 ft) by = 2.40 m (8 ft)

C.

=3 m (10 ft) by =2.74 m (9 ft)

D.

=3 m (10 ft) by =3.40 m (11 ft)

Question 6

Based on the estimated work area size, what is the MAXIMUM number of work areas that a telecommunications enclosure shall serve?

Options:

A.

20

B.

26

C.

32

D.

36

E.

40

Question 7

During program execution, a program manager receives feedback from an executive sponsor (hat some program stakeholders may not understand the intended benefits of the program. Which will provide the greatest value to clarify stakeholder perceptions?

Options:

A.

Performing a stakeholder analysis

B.

Updating the stakeholder communications requirements

C.

Redistributing the benefits management plan

D.

Redistributing the program charter

Question 8

A program sponsor is concerned about the status of high-priority risks and budget variances. The program manager should refer lo which of the following?

Options:

A.

Program status dashboard

B.

Program management plan

C.

Program performance report

D.

Program management information system (PMIS)