Which two of the following items MUST be included in a detailed SoW? (Select two options.)
A large program consists of several component projects and six project managers. The program governance board requests that all components within the program undergo user acceptance testing before being released to the production environment
Where should the program manager document this?
A program is in its execution phase when a component project manager suggests a potential change that could increase the financial benefit of the program. The program manager is hesitant to submit a change request, as it would extend the program schedule and require a scope change.
To whom should the change request be presented?
Company A acquires company B. which leads to a two-year program lo integrate the processes and systems Company B uses a different project management process, and the company's staff is unhappy about the acquisition As a result company B's project team fails to provide status and cost data in a format that conforms to the program standards.
What should the program manager do first?
The ICT distribution designer is hired to design a Telecommunications Room on the third floor of a building. The size of the floor is 20 m by 26 m (92 x 85 It). What is to be the MINIMUM size of the TR?
Based on the estimated work area size, what is the MAXIMUM number of work areas that a telecommunications enclosure shall serve?
During program execution, a program manager receives feedback from an executive sponsor (hat some program stakeholders may not understand the intended benefits of the program. Which will provide the greatest value to clarify stakeholder perceptions?
A program sponsor is concerned about the status of high-priority risks and budget variances. The program manager should refer lo which of the following?
A program manager notices that one project manager tends to withdraw during important team discussions to avoid conflict. What technique could the program manager use to gam more input from this project manager?
A telephone facility and an electrical facility are required in a tunnel. To reduce the effects of EMI and eliminate the need for additional shielding of the cables, where would each facility be placed?
An ICT distribution designer is reviewing design documents with the owner to gam approval for an ER design. Which of the following information about the site shall be included?
Which two of the following are ADVANTAGES of aerial pathways? (Select two options.)
To create market advantage, a program sponsor requests accelerating the implementation of a new manufacturing process that is based on a recently improved system component. The program manager is concerned that the delivery of some program goals could be jeopardized.
What should the program manager do?
A program manager is working on benefits. The program team created and updated a benefits register earlier in the program. The benefits register should include which of the following?
In an office area, a consultant needs to add the location of a fax machine to the plan. What is the approximated floor area that a fax machine occupies?
XYZ Company hires you to make its transitioning procedure more effective in meeting close-out requirements. You review XYZ's transitioning procedures to eliminate any that do not belong in the close-out phase.
Which of the following procedures should you removed?
Alter an organization initiates a strategic program several project managers express interest in joining the program Team. The program manager's supervisor recommends a list of project managers to be part of the team
What should the program manager do to select the project managers''
Throughout a multiyear program, component projects are transitioned to the customer. During the project acceptance phase, a potential risk is identified and brought to the program team's attention.
What should be done with the identified potential risk?
A program manager is identifying and verifying risks as outlined in the risk management plan. The results will be recorded in which of the following?
A program receives initial approval from the selection committee to proceed with the program development. What should the program manager do next"?
To increase its presence and promote its products and services in new markets, a company begins to implement its new business strategy. The company's CEO endorses a new program to promote and support this strategy However before the program is formally initialed, this strategy must be aligned with the organization's strategic goals and objectives.
What should the program manager develop first?
Exhibit:
A pay telephone using coins needs to be installed in a public area. In the specifications, it is required that the telephone shall meet the ADA (Americans with Disability Act) requirement for side reach using a wheelchair. What will be the maximum reachable height or the value of "X"?
A program manager is developing a program management plan by integrating the plans of constituent projects. During this effort, the program manager learns that a resource is critical to more than one component and there is a time overlap for their availability
When creating the program resource management plan, what should the program manager do first?
For a six story building (plus a basement) each of the six floors has a useable area of =3716 m2 (40.000 ft2) There are two riser systems, each serving halt of the useable area on each Moor What are the sleeves quantity and configuration required from fifth floor to sixth floor?
The size and number of conduits or sleeves used for backbone pathways depend on the usable floor space served by the backbone distribution system. What is the MINIMUM trade size of sleeves recommended to serve a TR, ER, or EF?
What is the RECOMMENDED bend radius of a conduit with an internal diameter of 51 mm (2 in)?
The program manager leads a medical billing system integration program for company A. a health services provider Company A acquires smaller company X. which delivers health services strategically aligned with company A Company X uses a different billing approach than company A. Company A's chief information officer (CIO) seeks counsel on which solution would be the better option moving forward requesting the program manager's assistance.
How should the program manager respond to the ClO's request1?
A program manager for the construction of an international event venue that will impact the local community needs to determine the best approach for communications. One of the conditions of the program is that after the event takes place a park will be built for the community's use.
What should the program manager do to ensure community support?
The program manager wants to increase the team's commitment to the program objectives. The program manager should do which of the following?
A program includes the development and shipping of 12 million product units over the next year. However, one program supplier has a history of overestimating its planned volume, which puts the product launch at risk
What should the program manager do to monitor and control the supplier?
An ICT distribution designer is preparing a price quote for a building design with multiple floors originally sized at 40.000 ft (3716 m2). While the designer is preparing the quote, the structural engineer indicates the building has been increased in size to accommodate an additional 40,000 ft2 (3716 m3) per floor. The designer's recommendation to the engineer will be to increase the slot area by_____for each additional 40,000 ft3 (3716 m2)
The type of apparatus housed in TRs varies greatly in size, purpose and function. Which two of the following active equipment is included? (Select two options.)
A design build firm has been retained by a client to construct an outpatient clinic. The client has hired an ICT distribution designer to review the DB firm's work product ensuring that the certified (mat documents are complete. In what capacity would the designer MOST LIKELY be serving?
A program manager evaluates conflicting stakeholder demands associated with cost, schedule, and intended benefits. The implementation team has a strong interest in cost and schedule, and a limited interest in the benefits being produced. The client is only focused on benefits.
Which of the following actions should the program manager take?
An organization is embarking on a new program aligned with its strategic objectives The new program has a High level of risk due to the rapidly changing technical landscape in which the organization operates The organization has mature program management capabilities, as measured by its resources, intellectual assets, and management processes.
Given the organization's history of delivering successful programs, what should the program manager do as part of the planning process?
Which two of the following may the ICT distribution designer need to provide in order to identify the BEST solutions for the client's need? (Select two options.)
A program manager has been assigned to a program that has received approval of the program charter and for which a stakeholder register has been prepared. During stakeholder engagement planning the program manager should consider which of the following stakeholder aspects?
How does a portfolio’s collection of work differ from that of a program's collection of work?
A program manager for an electronic gaming manufacturer is managing a new virtual reality program. An international trade agreement in the final stages of renegotiation will reduce supply-chain costs and delivery intervals A materials supplier informs the program manager that when this agreement is finalized, it will shorten the products delivery time.
What should the program manager update first?
A program manager recognizes that a successful resource being used in project A could also be used in project B. What should the program manager do first to leverage the utilization of this resource?
Communicating a project's design and technical specifications to the client and stakeholders is part of the ___________of the project.
An Ethernet passive optical network (EPON) uses an aggregation device called an optical line terminal (OLT). An OLT can support a MINIMUM of______subscribers per port using a passive optical splitter
Alter a company's senior executive management meeting the CEO issues a mandate to automate a new-client on-boarding process that would effectively eliminate the current manual paper-based process. The assigned program sponsor selects a program manager
Both the program sponsor and the program manager must ensure that the program charier contains which of the following?