A large program consists of several component projects and six project managers. The program governance board requests that all components within the program undergo user acceptance testing before being released to the production environment
Where should the program manager document this?
An Ethernet passive optical network (EPON) uses an aggregation device called an optical line terminal (OLT). An OLT can support a MINIMUM of______subscribers per port using a passive optical splitter
A program manager evaluates conflicting stakeholder demands associated with cost, schedule, and intended benefits. The implementation team has a strong interest in cost and schedule, and a limited interest in the benefits being produced. The client is only focused on benefits.
Which of the following actions should the program manager take?