Summer Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

CTAL-TM Exam Dumps : Certified Tester Advanced Level Test Management (CTAL-TM) v3.0

PDF
CTAL-TM pdf
 Real Exam Questions and Answer
 Last Update: May 9, 2025
 Question and Answers: 178 With Explanation
 Compatible with all Devices
 Printable Format
 100% Pass Guaranteed
$29.75  $84.99
CTAL-TM exam
PDF + Testing Engine
CTAL-TM PDF + engine
 Both PDF & Practice Software
 Last Update: May 9, 2025
 Question and Answers: 178
 Discount Offer
 Download Free Demo
 24/7 Customer Support
$47.25  $134.99
Testing Engine
CTAL-TM Engine
 Desktop Based Application
 Last Update: May 9, 2025
 Question and Answers: 178
 Create Multiple Test Sets
 Questions Regularly Updated
  90 Days Free Updates
  Windows and Mac Compatible
$35  $99.99

Verified By IT Certified Experts

CertsTopics.com Certified Safe Files

Up-To-Date Exam Study Material

99.5% High Success Pass Rate

100% Accurate Answers

Instant Downloads

Exam Questions And Answers PDF

Try Demo Before You Buy

Certification Exams with Helpful Questions And Answers

Certified Tester Advanced Level Test Management (CTAL-TM) v3.0 Questions and Answers

Question 1

Mary is an external IT auditor. She is conducting a review of the system-level testing done by Greg's functional testing team.

Which of the following items from Mary's assessment summary should concern Greg the most? [2]

Options:

A.

All the Business requirements could be traced to Test Objectives. However there was no tracing from the Business Requirements to the project's test

schedule.

B.

Some of the Test Objectives could only be mapped back to a single Business Requirement.

C.

A few of the Test Objectives did not have any Test Conditions assigned to them.

D.

There were Test Conditions which didn't tie back to any Business Requirement.

Buy Now
Question 2

You are the Test Manager of a four-person test team working for a small distribution company with a single warehouse. Your team has been working with a third party development team on a new

inventory management system. The company expects this system to generate approximately one million dollars per annum in profits for the company. Early in the project, various risks were

identified, and steps taken to mitigate those risks.

For example, you sent your test team for training on the new system, and upgraded the test environment. There are still some lingering risks that have not been addressed, but they have been

determined to have a low chance of occurring, with minimal impact if they do occur.

What would be the best option to mitigate these remaining risks? [3]

Options:

A.

Note the risks, and ignore them for now.

B.

Redo the project test plan to add additional testing for these risk items.

C.

Contract with the Risk Protection Insurance company to assume these risks at a cost of $500,000 per annum.

D.

Create a cross-functional team to work to reduce the impact and likelihood of these risks coming to fruition.

Question 3

Which of the following is a typical use of risk analysis? [1]

Options:

A.

Identifying the appropriate depth of testing for each identified risk

B.

Deciding what personnel should be assigned to which tests

C.

Determining the design of the tests used to mitigate each identified risk

D.

Forecasting the product delivery date