Delivery dates and availability of resources can be found in the details of the __________.
How many communication channels will be required in a project in which 5 individual are participating?
Which of the following provides the least accurate in estimating?
Which time estimating tools estimate the basis for activity durations can be quantitatively determined by multiplying the quantity of work to be performed by the productivity rate?
Which of the following are parts of project scope management?
Which of the following is conflict resolution technique?
Create Procurement document is done in _______.
You are the project manager of the MKTG Project. The project has a budget of $200,000 and is expected to last 2 years. The project is now 20 percent complete and is on schedule. What is the BAC?
Project just went into inclusion mode. This means that project __________.
If a project with a SPI of 1.8, what you tell?
Make-or-buy decisions measure the costs of both options. What are the two options?
Most change requests are a result of _______.
Which of the following is not a form a leadership power?
Which document is best suited for tracking the assignment of all resources to specific tasks in a project?
Which of the following does not provided by scope statement?
______________ provides details about how the project scope may be changed.
Which of the following are the inputs of Define Scope?
Which risk response is most likely to involve contingency reserves?
When you are developing the estimates for project, you choose to add the individual estimates for the activities that comprise each phase. What type of estimation method are you using?
What is the lowest level in a work breakdown structure?
Collect Requirements process starts in Project Planning Phase and uses the outputs of the __________.
Which of the following is NOT an input of close project process?
Who applies project selection methods to decide whether to accept or reject a project?
You are the project manager of a project and budgeted money to provide cash awards to team members that exceed expectations. A project team member that is motivated by the chance to earn cash reward can most accurately be explained by which theory
Assumptions are factors that, for planning purposes, are considered to be ______.
Which of the following is an input to Collect Requirements?
If the Schedule Variance (SV) =$55, and the Planned Value (PV) =$11, what is the Earned Value (EV)?
Based on the following metrics: EV=$20,000, AC=$22,000 and PV=$28,000, what is the project CV?
The initial development of a Project Scope Management plan uses which technique?
To which process is work performance information an input?
Which of the following is an input to the Qualitative Risk Analysis process?
Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?
Company A is launching a new communications satellite system. Resource B was assigned combined projects of design, construction, integration, and launch of the satellite.
Resource B's role is that of a:
What is a cost of nonconformance?
Which of the following will be required to perform simula-tion for schedule risk analysis?
Which of the following choices is a contract closure tool or technique?
Which of the following is a tool and technique for activity duration estimating?
The procurement document is an input to which of the following processes?
Which process involves identifying and documenting the logical relationships among schedule activities?
The risk register contains which of the following?
What is an output of Control Scope?
Company A bought a well-defined project deliverable from Company B. Company A will pay a fixed total price plus a percentage premium for the schedule target achieved.
For which type of contract have they subscribed?
What is one of the MAJOR outputs of activity sequencing?
What is one of the objectives of project risk management?
Forecasts, requested changes, recommended corrective actions, and organizational process asset updates are all outputs of which process?
Which estimating technique uses the actual costs of previous similar projects as a basis for estimating the costs of the current project?
What is a technique used in the performance reporting process?
Which of the following is involved in the initiation process group?
Which quality control technique illustrates the 80/20 Principle?
Providing forecasts to update current cost and schedule information is a part of which process?
In which type of organizational structure are staff members grouped by specialty?
You are project manager of a project and you are offering an estimate that you know will be changed after the contract is signed is ___________.
Identification of Mandatory Dependencies is done during which of the following process:
Which document formally authorizes a project?
A Reserve Analysis is a technique for:
When should a project manager be assigned to a project?
You are working with an organization and you found that one stakeholder not disclosing all of the costs involved with an upcoming project. Rather, this CAPM is constructing a WBS that does not include all the tasks necessary to get the project done. What you should do?
Which of the following activity is not performed as part of the direct and manage project execution process?
Which type of network diagram is also referred to Activity-on-Node (AON) diagrams?
The scope management provides:
If you are project manager for a Project and will need as many inputs to the initiation phase as possible. Of the following, which is the best source of information for your project?
How many communication channels will be required in a project in which 10 individual are participating?
What involves determining what quantities are to be used to perform project activities.
Information should be communicated to __________.
You are the project manager of a project. Your project just went into integration mode. This means that your project __________.
You are the project manager for a Project. Project is a global project. Some peoples are working from US and some are from India. Client says budget should not cost more than $12 million. Because of the global concerns, the final budget must be in U.S. dollars. This is an example of which of the following?
At which stage, stakeholders have the maximum influence on a project?
Which of the following is ensuring that all features and functions are included in a product or service
In which type of organization, a project manager is in complete control of the project?
A change requests can occur due to:
Which of the following is not a part of the project cost baseline but is included in the project budget?
You are the project manager for the software Project. This project must be completed within one year. This is an example of which of the following?
In PMBOK, the buyer is ________ to the project team.
Stakeholder influence is greatest at the ______ of the project.
Which of the following must be measured regularly to identify variances from the plan.
Project risk is defined as the cumulative effect of chances of ________ which will adversely affect project objectives.
Which of the following relationship is used in the Arrow Diagramming Method [ADM] :