Project risk is defined as the cumulative effect of chances of ________ which will adversely affect project objectives.
Likely events
Complex activities
Complex schedules
Uncertain occurrences
Uncertain occurrences can affect project objective.
Which of the following relationship is used in the Arrow Diagramming Method [ADM] :
Start-to-Finish
Finish-to-Start
Start-to-Start
Finish-to-Finish