New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Full Access PMI CA0-001 Tutorials

Page: 14 / 20
Total 525 questions

Certified Associate in Project Management (CAPM) Certification Questions and Answers

Question 53

You are project manager of a project and you are offering an estimate that you know will be changed after the contract is signed is ___________.

Options:

A.

Bad practice

B.

Unprofessional practice

C.

Bacl f°r both tne buyer and seller

D.

Al1 of the above

Question 54

Identification of Mandatory Dependencies is done during which of the following process:

Options:

A.

Sequence Activities

B.

Develop Schedule

C.

Define Activities

D.

Estimate Activity Durations

Question 55

Which document formally authorizes a project?

Options:

A.

The project charter

B.

Project scope statement

C.

The P'oject contract

D.

Project closing document

Question 56

A Reserve Analysis is a technique for:

Options:

A.

Estimate Activity Durations

B.

Estimate Activity Resources

C.

Sequence Activities

D.

Define Activities

Page: 14 / 20
Total 525 questions