Question 1

Which of the following statements is correct?

Options:

A.

An accuracy KPI that increases and a deviation KPI that increases is showing that your project is under control.

B.

An accuracy KPI that decreases and a deviation KPI that increases is showing that your project is under control.

C.

An accuracy KPI that decreases and a deviation KPI that decreases is showing that your project is under control.

D.

An accuracy KPI that increases and a deviation KPI that decreases is showing that your project is under control.

Buy Now
Question 2

What is ROLLO?

Options:

A.

Rollo is the official NI tool for planning and tracking a Customer Project rollout.

B.

Rollo is the official NI tool for risk management of a Customer Project rollout.

C.

Rollo is the official NI tool for sales forecasting of a Customer Project rollout.

D.

Rollo is the official NI tool for quality management of a Customer Project rollout.

Question 3

What are the main benefits of keeping an action point list of open/closed issues with your customer?

Options:

A.

A properly followed-up action point list can be used to increase sales and create business opportunities with this customer.

B.

Avoid duplication of effort, clear responsibilities and proper follow-up of identified issues.

C.

It serves as the basis for contingency reserves revision.

D.

The action point list serves as evidence for objective achievements.

Question 4

What needs to be updated after approved scope change request?

Options:

A.

Account plan.

B.

Risk management plan.

C.

Work break down structure.

D.

Communication plan.

Question 5

What are the main responsibilities of the Cost & Progress Manager (EVM)?

Options:

A.

To issue the Purchase Orders in atimely manner to subcontractors.

B.

to prepare the Baseline independently and present to PM for approval prior to project start.

C.

That invoices aretimely processed andto avoid delays to subcontractor payments.

D.

Cost control and monitoring, doing regular reviews with the Project Manager.

Question 6

Which of the following is the basic input needed for the negotiation of a contract with a new subcontractor?

Options:

A.

Procurement is responsible to use existing NSN guidelines in the contract.

B.

Clear PO issuance procedures, payment and acceptance terms.

C.

The conditions agreed in the Customer Contract.

D.

Assurance of subcontractor delivery capability in terms of resources and previous performance.

Question 7

Demand Planning meetings will generate inputs to:

Options:

A.

SAP, with impacts to sales estimations.

B.

Rollo, with impacts to volumes estimations.

C.

MRA, with impact to resource allocations to project team.

D.

Nelle, with impacts to Supply Chain and PRS(Profitability Reporting System) figures.

Question 8

What are examples of relevant inputs to Project Plan preparation?

Options:

A.

PMBok.

B.

Customer RFQ and Customer Implementation Requirements (priority, site specifications), besides the sub plans that PM considers relevant.

C.

Cost Plan, Schedule and Quality Plan.

D.

All inputs defined in the NSN Project Plan Template.

Question 9

What is RTI?

Options:

A.

Interface between Site quality module and IPM.

B.

Interface between SAP and IPM.

C.

An external database linking SAP and E-doc

D.

Interface between Change management and Quality module.

Question 10

How frequently is an update of the "Cost Estimation at Completion" required?

Options:

A.

Each time there is a change in the scope of work.

B.

Each time there is a change in the schedule or scope of work.

C.

At least once per month, preferably before period end.

D.

Every quarter before PRS(Profitability Reporting System) results are published.

Question 11

When can the project management plan be modified?

Options:

A.

Up to the start of project execution, from then on the project management plan must be frozen as a baseline for future reference.

B.

In case the scope of work has changed.

C.

Over time during the project as it has at any time to reflect the latest status of the agreed practices, processes and responsibilities.

D.

When the PM receives the handover from Sales do Delivery.

Question 12

Which of the following items is NOT part of the IPM suite?

Options:

A.

Sales Management.

B.

Site Data Management.

C.

Change Management.

D.

Document Management.

Question 13

What are the defined Gates in the NSN Sales Work Flow?

Options:

A.

1. Customer Selection

2. Go/No Go

3. Bid/No Bid

4. Approval/No Approval

5. Deal/No Deal

6. Start Delivery

B.

1. Receive the RFQ

2. Define Bid Team

3. Create Customer Offer

4. Negotiate Contract

5. Prepare Project Plan

C.

1. Identify Customer Needs

2. Develop a Solution

3. Prepare Commercial Offer

4. Negotiate Contract

5. Prepare PTA

D.

1. Receive RFQ

2. Develop Solution

3. Prepare Commercial Offer

4. Negotiate Contract

5. Prepare for Delivery

Question 14

Project team received from the Sales Team the Risk Log at Handover, which is the base for the planned contingency reserves. During project execution a new relevant risk is identified. What is the best way to manage it?

Options:

A.

Evaluate the impact and probability and, if needed, make a revision of the contingency reserves in the Cost Baseline, of the EAC and communicate to the relevant stakeholders.

B.

If the new risk is not part of the current Risk Log, than it must be part of a Change Management process and not be included in the contingency reserves.

C.

Communicate to the CT Head in the next Project Review Meeting about the new risk that has been identified.

D.

Define the response plan for the new Risk and apply it.

Question 15

What are the key elements that must be monitored constantly over the entire project life cycle?

Options:

A.

Quality and Subcontractor Performance.

B.

Contract conditions and Project Deliverables.

C.

Cost, Time and Scope.

D.

Financial Reports and Schedule.

Question 16

What are the components of Latest Estimate in PRS(Profitability Reporting System)?

Options:

A.

Sales, Cost of Sales and Gross Profit.

B.

Sales, Volumes and Cost of Sales.

C.

Actual results of the Previous Period.

D.

Baseline, ETC and EAC.

Question 17

What is the KPI generated from the forecast data in ROLLO?

Options:

A.

P-SQI

B.

RA

C.

SILT

D.

TILT

Question 18

What needs to be included in the project cost base line of the Gate 4?

Options:

A.

All risk values captured during risk management workshops.

B.

All costs related to risk mitigation plans.

C.

All costs of risk management agreed between the sales account manager and service delivery responsible.

D.

All costs related to risk contingency plans.

Question 19

When does the PM need to update ROLLO with customer/project data?

Options:

A.

After the customer forecast is received.

B.

At year end.

C.

At least once a month, before period cut-off.

D.

Per STP.

Question 20

Which of the following information can NOT be extracted from Rollo?

Options:

A.

Volume of sites per project planned for the period.

B.

List of site names forecasted for the coming period.

C.

Actual number of sites integrated per technology.

D.

Accuracy metric of planned versus actual completed sites.

Question 21

NSN is under pressure to keep Customer deadlines but PO has not yet been received. Under what circumstances can a PO be issued to the subcontractor?

Options:

A.

If the deadline is really critical for the Customer, PM must take the responsibility to execute the Rollout.

B.

PM must escalate the issue and request for a formal approval from CT.

C.

PM requests subcontractor to start work without NSN PO - that will be issued when we get out PO from the Customer.

D.

PM will not subcontract services without a Customer PO.

Question 22

What would be the preferred course of actions when you find out that the project Gross Margin is showing a lower figure in PRS(Profitability Reporting System) than what you expected?

Options:

A.

Escalate the problem to the CT Head.

B.

Request the CPM to prepare a detailed presentation about project costs.

C.

Invite the CPM and Project F&C to identify the deviations and review if cost and revenue have been correctly reported in PRS according to the Demand Plan assumptions and Project Cost calculations.

D.

Start a cost reduction plan and reduce headcount.

Question 23

What milestones are used to calculate SILT?

Options:

A.

IS13.1 Main Equipment on site and Last Customer Invoice Trigger.

B.

IS13.1 Main Equipment on site and Provisional Acceptance.

C.

Date of equipment shipped to the site and Date of Invoice Received by the Customer.

D.

IS13.1 Main Equipment on site and Internal Acceptance.

Question 24

Which of the following options describes the basic sequence of turnkey site process phases?

Options:

A.

1. Site Search 2. Site Selection 3. Permitting 4. Site Design 5. Leasing 6. Construction Works 7. Telecom Implementation 8. Site Acceptance

B.

1. Site Design 2. Site Search 3. Site Selection 4. Leasing 5. Permitting 6. Construction Works 7. Telecom Implementation 8. Site Acceptance

C.

1. Site Search 2. Site Acceptance 3. Leasing 4. Site Design 5. Permitting 6. Construction Works 7. Telecom Implementation 8. Network Optimization

D.

1. Site Search 2. Site Selection 3. Leasing 4. Site Design 5. Permitting 6. Construction Works 7. Telecom Implementation 8. Site Acceptance