Question 21

NSN is under pressure to keep Customer deadlines but PO has not yet been received. Under what circumstances can a PO be issued to the subcontractor?

Options:

A.

If the deadline is really critical for the Customer, PM must take the responsibility to execute the Rollout.

B.

PM must escalate the issue and request for a formal approval from CT.

C.

PM requests subcontractor to start work without NSN PO - that will be issued when we get out PO from the Customer.

D.

PM will not subcontract services without a Customer PO.

Question 22

What would be the preferred course of actions when you find out that the project Gross Margin is showing a lower figure in PRS(Profitability Reporting System) than what you expected?

Options:

A.

Escalate the problem to the CT Head.

B.

Request the CPM to prepare a detailed presentation about project costs.

C.

Invite the CPM and Project F&C to identify the deviations and review if cost and revenue have been correctly reported in PRS according to the Demand Plan assumptions and Project Cost calculations.

D.

Start a cost reduction plan and reduce headcount.

Question 23

What milestones are used to calculate SILT?

Options:

A.

IS13.1 Main Equipment on site and Last Customer Invoice Trigger.

B.

IS13.1 Main Equipment on site and Provisional Acceptance.

C.

Date of equipment shipped to the site and Date of Invoice Received by the Customer.

D.

IS13.1 Main Equipment on site and Internal Acceptance.

Question 24

Which of the following options describes the basic sequence of turnkey site process phases?

Options:

A.

1. Site Search 2. Site Selection 3. Permitting 4. Site Design 5. Leasing 6. Construction Works 7. Telecom Implementation 8. Site Acceptance

B.

1. Site Design 2. Site Search 3. Site Selection 4. Leasing 5. Permitting 6. Construction Works 7. Telecom Implementation 8. Site Acceptance

C.

1. Site Search 2. Site Acceptance 3. Leasing 4. Site Design 5. Permitting 6. Construction Works 7. Telecom Implementation 8. Network Optimization

D.

1. Site Search 2. Site Selection 3. Leasing 4. Site Design 5. Permitting 6. Construction Works 7. Telecom Implementation 8. Site Acceptance