11.11 Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

CompTIA PK0-004 Exam With Confidence Using Practice Dumps

Exam Code:
PK0-004
Exam Name:
CompTIA Project+ Exam
Certification:
Vendor:
Questions:
796
Last Updated:
Nov 17, 2024
Exam Status:
Stable
CompTIA PK0-004

PK0-004: Project+ Exam 2024 Study Guide Pdf and Test Engine

Are you worried about passing the CompTIA PK0-004 (CompTIA Project+ Exam) exam? Download the most recent CompTIA PK0-004 braindumps with answers that are 100% real. After downloading the CompTIA PK0-004 exam dumps training , you can receive 99 days of free updates, making this website one of the best options to save additional money. In order to help you prepare for the CompTIA PK0-004 exam questions and verified answers by IT certified experts, CertsTopics has put together a complete collection of dumps questions and answers. To help you prepare and pass the CompTIA PK0-004 exam on your first attempt, we have compiled actual exam questions and their answers. 

Our (CompTIA Project+ Exam) Study Materials are designed to meet the needs of thousands of candidates globally. A free sample of the CompTIA PK0-004 test is available at CertsTopics. Before purchasing it, you can also see the CompTIA PK0-004 practice exam demo.

CompTIA Project+ Exam Questions and Answers

Question 1

In a weak matrix, a highly skilled project team member has been using company equipment to view inappropriate content. Which of the following steps should the project manager take FIRST to address this issue?

Options:

A.

Send an email outlining the company’s acceptable use policy to the employee.

B.

Arrange a face-to-face meeting with the team member.

C.

Contact the team member’s manager to address the problem.

D.

Restrict the team member’s equipment access.

Buy Now
Question 2

Given the status report excerpt below:

Overall status: The project is tracking well. Tasks are being completed on time. Costs are lower than expected. Risk/issues are regularly being monitored are tracked.

Which of the following MOST likely is occurring in the project?

Options:

A.

The project manager forgot to update the risks/issues status.

B.

The project has experienced a risk trigger recently that may impact the project very soon.

C.

There is nothing out of the ordinary; the project is progressing as expected.

D.

The project manager did not include any risks/issues detail because it is yellow and not red.

Question 3

Upper management asks a project sponsor to provide several ad hoc reports as a brief overview of the project’s current status.

Which of the following types of reports should the project sponsor use to quickly summarize the status report data?

Options:

A.

Pie chart

B.

Run chart

C.

Project schedule

D.

Dashboard information