New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Free and Premium Scrum PSM-II Dumps Questions Answers

Page: 1 / 5
Total 74 questions

Professional Scrum Master II Questions and Answers

Question 1

What are acceptable ways a Scrum Master may work to ensure Scrum is understood and enacted?

(choose the best three answers)

Options:

A.

Arrange one-on-one coaching sessions where concerns the Scrum Master has identified can be discussed.

B.

Hold longer, more in-depth retrospectives with formal learning as part of the retrospective.

C.

Schedule group training about Scrum.

D.

Require senior management to mandate that all teams in the organization must follow and enact Scrum.

E.

Educate stakeholders and customers about Scrum.

Buy Now
Question 2

After some small experiments with Scrum, your company decides to do a complete project with Scrum. As Scrum Master; you have been invited to the "project kick-off meeting" with IT and product management

The Product Owner asks how many Sprints IT will need to first figure out architecture and infrastructure issues. What are two options to explain how such work is managed using Scrum?

(choose the best two answers)

Options:

A.

You explain that product management should not worry about such typical IT work. You inform them that you will assure that the team members reach out to the right people within the IT organization when needed During each Sprint Planning event they will keep the Product Owner updated about the additional effort it will take for that Sprint. That effort will come on top of the effort for the forecasted functional development.

B.

You explain that technical risks are best controlled when architecture and infrastructure emerge alongside the development of functionality. The additional advantage is that business value is created faster and sooner.

C.

You thank product management for understanding that these efforts indeed require effort and budget You confirm that architecture and infrastructure are best addressed before starting Scrum, but that the exact budget is difficult to calculate upfront You say you will organize this work in timeboxed Sprints of no more than 30 days to limit risk and be transparent toward product management on the actual progress.

D.

You educate the Product Owner to add this work to the Product Backlog to uphold transparency. Ask the Developers to plan work during the first several Sprints to estimate these items, while also creating some business functionality in these early Sprints

Question 3

A multi-national company is using Scrum for product development of their five major products.

What alternatives should the company consider to decide how many Product Owners are needed for these five products?

(choose the best two answers)

Options:

A.

There is one Product Owner for each product (five in total). Each Product Owner may delegate to others for specific value, capabilities, and functionality within their product. The five Product Owners share and align work via Product

Backlog.

B.

There are as many Product Owners as needed to analyze, document, and

explain expectations and requirements with all Scrum Teams.

C.

There is one Product Owner for all five products. This person may not delegate work to others for specific value, capabilities, and functionality, given these are all the Product Owner's individual responsibility.

D.

There is one Product Owner responsible for all five products. This person may

delegate work to others for specific value, capabilities, and functionality within each product to scale their accountability.

Question 4

A Scrum Team consists of Developers working from globally distributed locations. Organizing the Scrum events requires conferencing tools that are not easily available within the organization. The Developers propose doing a Daily Scrum only on Tuesdays. Which are the most appropriate responses for their Scrum Master?

(choose the best two answers)

Options:

A.

Help the Developers understand that lowering the frequency of communication will only increase the feeling of disconnect between the team members.

B.

Coach the Developers on why a daily frequency is important as an opportunity to update the Sprint Plan and how it helps the team organize work toward achieving the Sprint Goal.

C.

Acknowledge and support this self-managing team's decision

D.

Have the Developers vote to make sure there is consensus within the team

Question 5

At the seventh Sprint Review, the stakeholders seem disappointed and angry. When asked about it, they say the product being built will not meet their needs and will cost more than they anticipated spending. What factors may have led to this?

(choose the best three answers)

Options:

A.

The stakeholders have not been using the Sprint Reviews to actively engage, and inspect and evaluate progress.

B.

The stakeholders were not allowed to enter the development area, or be present at the Daily Scrum.

C.

The Project Management Office (PMO) and its project managers have not been adequately engaged, causing the project plan to become inaccurate.

D.

The Scrum Master has not ensured transparency.

E.

The Product Owner has not been interacting frequently with the stakeholders and kept them aware of the progress of the project.

F.

Changes to the project plan were not adequately documented and shared. The change request procedure was not diligently followed.

Question 6

Which two of these situations best demonstrate that a Scrum Team is self-managing?

(choose the best two answers)

Options:

A.

Developers collaboratively select and re-plan their work during the Sprint.

B.

The Scrum Team invites the right external people to the Sprint Planning to help them create a complete and detailed Sprint Backlog before the meeting timebox expires.

C.

The Developers create their own Sprint Backlog, reflecting all work that is part of the Definition of Done.

D.

Management is invited to the Daily Scrum for a progress update and

subsequently works with the Scrum Master to optimize the plan for the next day.

E.

The Developers are strictly working within the boundaries of their function description, and are handing off work in a timely fashion to the other members within the team.

Question 7

You have just been hired as a Scrum Master by a company new to Scrum. The company wants to use Scrum to build a new product that was conceived by the product management department. You will be the Scrum Master of two new teams that will build a first version of the product. The product management department assigns two new Product Owners, but wants more advice about the required participation with the new Scrum Teams. Which two suggestions would you offer?

(choose the best two answers)

Options:

A.

Having one Product Owner will improve the clarity of accountability to the teams and to the product management department.

B.

Two Product Owners are necessary, one for each Scrum Team. They report to an overarching chief Product Owner.

C.

Each Scrum Team has a separate Product Backlog, holding each team's assigned requirements.

D.

A single Product Backlog should be maintained holding all requirements for the new product.

Question 8

You are a Scrum Master and one of the Developers approaches you and says: Every Sprint we are not completing regression testing for all of the selected Product Backlog items in the Sprint, but regression testing is part of the Definition of Done. We have discussed with the Product Owner and during the Sprint we decided to change the Definition of Done to remove regression testing. Which two actions are appropriate in this situation?

(choose the best two answers)

Options:

A.

Agree with altering the Definition of Done, if both the Developers and Product Owner agree.

B.

Ask the Developers and the Product Owner if removing regression testing from the Definition of Done allows the team to produce useful and valuable Increments at the end of every Sprint?

C.

Ask the Developers and the Product Owner what problem they are going to solve by altering the Definition of Done during the Sprint to remove regression testing. Will this raise transparency or improve quality?

D.

Disagree with the decision and tell them that having a stringent Definition of Done is important for the quality of the product, and they need to follow it.

Question 9

Your organization always stresses the importance of on-time delivery and reliability. A manager has detected that your team's progress is too slow. They feel that your team's velocity needs to be 10% higher.

The organization expects you, as the Scrum Master, to make it happen. How do you respond?

(choose the best two answers)

Options:

A.

You educate management that it is the Scrum Team's responsibility to improve their velocity. You invite management to the next Sprint Retrospective to brainstorm on how they can improve.

B.

You inform management of organizational impediments that prevent the Scrum Team from being more productive. You enlist their help to remove these impediments.

C.

You explain how a Scrum Team uses the velocity of a Sprint primarily to forecast work for the next Sprint, not to perfectly predict future productivity. You refer management to the Product Owner for all information concerning the progress of development.

D.

You tell management that this is not your accountability in Scrum. You direct them to the Product Owner to determine whether the forecast is accurate.

E.

You help management understand that it typically takes a few Sprints for a team to gradually increase the velocity up to the level expected. Meanwhile you present this to the team as a challenge and a company goal, leaving it however up to them to figure out exactly how to achieve this.

Question 10

You are a Scrum Master entering an organization that wants to "evolve" their product development to Scrum. The organization's teams are organized into component teams. This means that teams address one single application layer only (for example, front end, middle tier,

back end, and interfaces).

You introduce the concept of feature teams, where teams have the skills to work on multiple layers throughout a Sprint and deliver working software every Sprint. What are two things you take into consideration when moving away from component teams toward feature teams?

(choose the best two answers)

Options:

A.

You cannot do Scrum without feature teams. Do not continue adopting Scrum until teams are reorganized in feature teams.

B.

Productivity, in terms of lines of code or story points, will probably suffer during the transition, although even then delivery of business value is still likely to Increase.

C.

Feature teams will require time to become productive as people from the different layers and components become accustomed to working and delivering unified functionality together, as one Scrum Team.

D.

With feature teams, it is easier to calculate and compare the productivity per team. Incentives on productivity are likely to speed up the transition to feature teams, and therefore the adoption of Scrum.

Question 11

You are the Scrum Master for three Scrum Teams working on the same product. There is a single Product Backlog that all three Scrum Teams select from. Management is eager to improve the productivity of the teams and wants to standardize velocity across all three teams so that they can see how each team is delivering value. When responding to management, which two statements are appropriate?

(choose the best two answers)

Options:

A.

Incentivizing teams based on velocity can boost the Scrum Team's motivation to create more value.

B.

Standardizing velocity across teams can help with understanding which teams

are creating more value.

C.

Velocity has no direct relationship with value.

D.

Velocity is the amount of business functionality that a Scrum Team creates in a Sprint. It is unique to that team and used as an input to Sprint Planning.

Question 12

Which of the following affect the outcome of a Sprint?

(choose all that apply)

Options:

A.

The complexity of the problem being solved.

B.

The complexity of the requirements.

C.

The skills and working relationships of the people on the Scrum Team(s).

Question 13

True or False: Using Scrum ensures that adding more resources to a project proportionally increases the value delivered.

Options:

A.

True

B.

False

Question 14

In the Sprint Retrospective, there is discussion that the quality of the Increment is not sufficient tor going to production In response, a Scrum Team member points out the high velocity reached by the team. What are the two best actions tor the Scrum Master to take?

(choose the best two answers)

Options:

A.

Agree and praise the Developers for their nard work, so they are motivated to do even more in the next Sprint

B.

Facilitate a discussion on now to improve the quality to a level sufficient tor production, even it the measured velocity will drop in the next Sprint

C.

Acknowledge the nard work, but remind the Developers that they need to

improve to do even more in the next Sprint.

D.

Stress the value of working product over measured velocity.

Question 15

A Scrum Team selected a Product Backlog item during Sprint Planning. However, at the end of the Sprint the work does not meet the Definition of Done. What two things should happen with this incomplete Product Backlog item?

(choose the best two answers)

Options:

A.

Review the item, add the done part of the estimate to the velocity and create a Story for the remaining work.

B.

The item is not included in the Increment for this Sprint.

C.

Only the stakeholders decide over acceptance of undone work and whether to

release it.

D.

It is put on the Product Backlog for the Product Owner to decide what to do with it.

Question 16

True or False: When scaling Scrum it is important to have multiple Scrum Teams working from one Product Backlog

Options:

A.

True

B.

False

Question 17

Which four of the following risks to product development are addressed by Scrum?

(choose the best four answers)

Options:

A.

The timescale of the planned work.

B.

The stability and complexity of the technology.

C.

The complexity and unpredictability of the requirements.

D.

The skills and working relationships of the people on the teams.

E.

The definition of incentive and bonus strategies by Human Resources for all

team members.

F.

The clear definitions of stages and gateways in the overall governance model.

Question 18

Scrum requires a Definition of Done. Which phrases describe the purpose of the Definition of Done?

(choose the best three answers)

Options:

A.

It serves to track the percent completeness of a Product Backlog item during the Sprint.

B.

During the Sprint it helps the Developers identify the work remaining for an

Increment to be ready for release by the end of a Sprint.

C.

It creates transparency into the state of the Increment when it is inspected at the Sprint Review.

D.

It guides the Developers when creating a forecast at the Sprint Planning.

E.

It provides a template for the documentation of the product Increment.

F.

It is a checklist to inspect whether the Developers have performed their tasks by the end of a Sprint.

Question 19

You are the Scrum Master of a Scrum Team that is new to Scrum. The Product Owner comes to you halfway through the Sprint and says, "l do not feel like the De-velopers will be able to meet the forecast that they developed during Sprint Planning." What should you do in this situation?

(choose the best answer)

Options:

A.

Coach the Product Owner that achieving the Sprint Goal is the Scrum Team's objective. A forecast is only used to initially estimate the effort required to reach the Sprint Goal.

B.

Agree to help the Product Owner by having a discussion with the Developers about the importance of meeting their forecast.

C.

Add more people to the Scrum Team to meet the Product Owner's ex-pectations.

D.

Talk to the Developers. Challenge and inspire them to complete all of the work so that they meet their forecast.

Question 20

The relationship between the Product Owner and the Developers has degraded over time.

The Developers are growing increasingly angry with the Product Owner for changing the requirements all the time and not being available enough. The Product Owner is angry with the Developers for changing requirements during implementation. What guidance should the Scrum Master offer?

(choose the best answer)

Options:

A.

Take everyone to a 2-day off-site event to relax and re-align. It is liberating to take people's minds away from work.

B.

Ask each person's functional manager to instruct their employees that they must collaborate better, or be removed from the team.

C.

Address why requirements change during the Sprint Retrospective. Ask the

Developers and the Product Owner to talk about why the requirements are changing

and consider the impact on value during this discussion.

D.

Ask for a project manager or other external resource to mediate and temporarily take over for the Product Owner.

Page: 1 / 5
Total 74 questions