New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Pass Using PSM-II Exam Dumps

Page: 5 / 5
Total 74 questions

Professional Scrum Master II Questions and Answers

Question 17

Which four of the following risks to product development are addressed by Scrum?

(choose the best four answers)

Options:

A.

The timescale of the planned work.

B.

The stability and complexity of the technology.

C.

The complexity and unpredictability of the requirements.

D.

The skills and working relationships of the people on the teams.

E.

The definition of incentive and bonus strategies by Human Resources for all

team members.

F.

The clear definitions of stages and gateways in the overall governance model.

Question 18

Scrum requires a Definition of Done. Which phrases describe the purpose of the Definition of Done?

(choose the best three answers)

Options:

A.

It serves to track the percent completeness of a Product Backlog item during the Sprint.

B.

During the Sprint it helps the Developers identify the work remaining for an

Increment to be ready for release by the end of a Sprint.

C.

It creates transparency into the state of the Increment when it is inspected at the Sprint Review.

D.

It guides the Developers when creating a forecast at the Sprint Planning.

E.

It provides a template for the documentation of the product Increment.

F.

It is a checklist to inspect whether the Developers have performed their tasks by the end of a Sprint.

Question 19

You are the Scrum Master of a Scrum Team that is new to Scrum. The Product Owner comes to you halfway through the Sprint and says, "l do not feel like the De-velopers will be able to meet the forecast that they developed during Sprint Planning." What should you do in this situation?

(choose the best answer)

Options:

A.

Coach the Product Owner that achieving the Sprint Goal is the Scrum Team's objective. A forecast is only used to initially estimate the effort required to reach the Sprint Goal.

B.

Agree to help the Product Owner by having a discussion with the Developers about the importance of meeting their forecast.

C.

Add more people to the Scrum Team to meet the Product Owner's ex-pectations.

D.

Talk to the Developers. Challenge and inspire them to complete all of the work so that they meet their forecast.

Question 20

The relationship between the Product Owner and the Developers has degraded over time.

The Developers are growing increasingly angry with the Product Owner for changing the requirements all the time and not being available enough. The Product Owner is angry with the Developers for changing requirements during implementation. What guidance should the Scrum Master offer?

(choose the best answer)

Options:

A.

Take everyone to a 2-day off-site event to relax and re-align. It is liberating to take people's minds away from work.

B.

Ask each person's functional manager to instruct their employees that they must collaborate better, or be removed from the team.

C.

Address why requirements change during the Sprint Retrospective. Ask the

Developers and the Product Owner to talk about why the requirements are changing

and consider the impact on value during this discussion.

D.

Ask for a project manager or other external resource to mediate and temporarily take over for the Product Owner.

Page: 5 / 5
Total 74 questions