Under what circumstances can you change the material type for a material if stocks, reservations, or purchasing documents exist? Note: There are 2 correct answers to this question.
You want to use capacity availability checks for production orders. Which settings have to be made for this? Note: There are 2 correct answers to this question.
What does forecasting in the demand planning cycle include? Note: There are 3 correct answers to this question.
Which time elements are relevant for lead time scheduling of a production order? Note: There are 2 correct answers to this question.
Which of the following automation options can you use for production orders? Note: There are 2 correct answers to this question.
You want to insert an operation at a certain time on a work center in the graphical planning table. The planning direction is forward. The desired dispatching time coincides with an operation that has previously been dispatched. How does the insertion take place?
Which of the following elements does MRP take into account during net requirement calculation? Note: There are 2 correct answers to this question.
You want to set up a make-to-order planning scenario for a finished product. The bill of material contains two components: one should be procured for each sales order individually, and the other should be procured jointly for all independent requirements. Forecasting for the finished product is NOT possible. Which settings do you make to achieve this?
How can you support a GMP (Good Manufacturing Practice) compliant production process? Note: There are 3 correct answers to this question.
Your company manufactures materials whose characteristics differ for each manufacturing process. Which application do you have to use in SAP S/4HANA Cloud Private Edition to be able to track and use this information in all areas of logistics?
Which time elements does MRP consider in backward scheduling to determine the basic dates for components from dependent requirements? Note: There are 2 correct answers to this question.
What time element of midpoint scheduled operations can be reduced by reduction strategy settings while dispatching? Note: There are 2 correct answers to this question.
You have maintained the parameters for simple discontinuation in the material master of a component. Which business process will be affected if the available stock is zero and the discontinuation date is in the past?
Which alternative item strategies are available in bills of material (BOMs) in SAP S/4HANA Cloud Private Edition? Note: There are 2 correct answers to this question.
How can you achieve a feasible production plan in case of capacity constraints? Note: There are 3 correct answers to this question.
You are a consultant on an SAP S/4HANA Cloud Greenfield project. Which of the following aspects should you focus on to achieve and maintain clean core data quality? Note: There are 2 correct answers to this question.
You use planning strategy Finite Scheduling with Reverse and want to allow scheduling in the past. How can you parameterize this in the strategy profile?
What are the key features of using a low-level code? Note: There are 2 correct answers to this question.
Where do you maintain the data to determine the duration of an operation for production? Note: There are 2 correct answers to this question.
Where does the system check master data selection settings during the creation of planned orders or production orders? Note: There are 3 correct answers to this question.
You are trying to create a production order, but NO valid production version can be selected. What could be the reasons? Note: There are 2 correct answers to this question.
What is the difference between co-products and by-products? Note: There are 2 correct answers to this question.
In your plant MRP is activated. Which options do you have to exclude a material from the MRP run? Note: There are 2 correct answers to this question.
How can a material availability check be triggered automatically for a production order? Note: There are 2 correct answers to this question.