Black Friday Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Free and Premium SAP C_TS422_2023 Dumps Questions Answers

SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing Questions and Answers

Question 1

In your plant MRP is activated.

Which options do you have to exclude a material from the MRP run? Note: There are 2 correct answers to this question.

Options:

A.

Use a specific MRP list.

B.

Use a specific material status.

C.

Use a specific material group.

D.

Use a specific MRP type.

Buy Now
Question 2

What can you use stard heuristics in Advanced Planning (PP/DS) for?

Options:

A.

To automate material movements in material staging

B.

To set default values in production master data

C.

To solve planning problems for defined objects

D.

To optimize costs times in production plans

Question 3

What could be the reason for different combinations of components in a multiple bill of material (BOM)? Note: There are 2 correct answers to this question.

Options:

A.

Manufacturing date

B.

BOM header status

C.

BOM component status

D.

Lot size

Question 4

Where do you maintain the work center that represents the production line for repetitive manufacturing? Note: There are 2 correct answers to this question.

Options:

A.

Production cost collector

B.

Production version

C.

Repetitive manufacturing profile

D.

Routing

Question 5

Advanced Planning uses master data from SAP S/4HANA Cloud Private Edition. In which data objects can you set the Advanced Planning flag? Note: There are 2 correct answers to this question.

Options:

A.

Work center

B.

Plant

C.

Production version

D.

Material

Question 6

How can you set up a material as a phantom assembly? Note: There are 2 correct answers to this question.

Options:

A.

Select a special procurement type inside the material master.

B.

Use a special item category in your material BOM (bill of material).

C.

Select a special MRP type inside the material master.

D.

Define the special procurement type inside the material BOM (bill of material).

Question 7

Which information is required when you create a product master in SAP S/4HANA Cloud Private Edition? Note: There are 2 correct answers to this question.

Options:

A.

Base unit of measure

B.

Industry sector

C.

Selection screen for views

D.

Product type

Question 8

Under what circumstances can you change the material type for a material if stocks reservations or purchasing documents exist? Note: There are 2 correct answers to this question.

Options:

A.

The quantity value updates are the same.

B.

The same batch management level is used.

C.

The same base unit of measure is used.

D.

The same account category is used.

Question 9

What could be the reason for multiple commitments where several operations have the same scheduled dates on a work center after dispatching? Note: There are 2 correct answers to this question.

Options:

A.

The Finite Scheduling indicator is NOT set in the strategy profile.

B.

The work center has several individual capacities.

C.

Alternative work centers are fully occupied.

D.

The Change Planning Direction indicator is set in the strategy profile.

Question 10

Your company produces a finished good based on a forecast expects it to be in stock when customers order it. If customers order more than the forecasted quantity this must NOT have any impact on the production program.

Which planning strategy do you use?

Options:

A.

Assembly processing with production orders (82)

B.

Planning with final assembly (40)

C.

Planning without final assembly (50)

D.

Maketostock production (10)

Question 11

Your production planners are allowed to execute planning only for specific resources. How can you achieve this in Advanced Planning (PP/DS)?

Options:

A.

Use a resource group.

B.

Use a planning group.

C.

Use a propagation range.

D.

Use a planning area.

Question 12

Which of the following automation options can you use for production orders? Note: There are 2 correct answers to this question.

Options:

A.

You can use trigger points to automatically create rework orders via confirmations.

B.

You can use mass processing to set production orders to technically complete.

C.

You can use the production scheduling profile to automatically set orders to technically complete.

D.

You can use mass processing to read PP master data for production orders.

Question 13

Which time elements are relevant for lead time scheduling of a production order? Note: There are 2 correct answers to this question.

Options:

A.

Opening period

B.

Total replenishment lead time

C.

Float after production

D.

Setup time

Question 14

How can you limit the validity of a bill of material (BOM)? Note: There are 2 correct answers to this question.

Options:

A.

By material type

B.

By plant

C.

By period

D.

By material status

Question 15

Your company manufactures materials whose characteristics differ for each manufacturing process.

Which application do you have to use in SAP S/4HANA Cloud Private Edition to be able to track use this information in all areas of logistics?

Options:

A.

Process order management

B.

Engineering change management

C.

Quality management

D.

Batch management

Question 16

Which stard item categories can you select inside a bill of material (BOM)? Note: There are 2 correct answers to this question.

Options:

A.

Variablesize item

B.

Work item

C.

Preliminary item

D.

WBS item

Question 17

You use planning strategy Finite Scheduling with Reverse want to allow scheduling in the past. How can you parameterize this in the strategy profile?

Options:

A.

Specify a negative offset time.

B.

Specify a negative opening period.

C.

Specify a negative planning horizon.

D.

Specify a negative PP/DS horizon.

Question 18

What are the options if the Dispatched operation status is set for a production order operation? Note: There are 2 correct answers to this question.

Options:

A.

You can reschedule the operation using lead time scheduling.

B.

You can reschedule the operation using infinite scheduling in a planning table.

C.

You can reschedule the operation using finite scheduling in a planning table.

D.

You can reschedule the operation in the Manage Work Center Capacity app.

Question 19

Which actions does the system perform by default when you save a confirmation for a finished product in repetitive manufacturing? Note: There are 3 correct answers to this question.

Options:

A.

Post the goods receipt for the finished product.

B.

Reduce run schedule quantities.

C.

Post production costs to the planned order.

D.

Update statistics for the Business Information Warehouse.

E.

Create associated capacity requirements.

Question 20

What data can you maintain in the subitems of a bill of material (BOM)? Note: There are 2 correct answers to this question.

Options:

A.

Quantity

B.

Status

C.

Installation point

D.

Scrap percentage

Question 21

You are trying to create a production order NO valid production version can be selected. What could be the reasons? Note: There are 2 correct answers to this question.

Options:

A.

The order lot size is NOT within the validity range of a production version.

B.

NO production lines are assigned to the production versions.

C.

All production versions for the material are locked.

D.

NO bills of material (BOMs) are assigned to the production versions.

Question 22

Which of the following questions do you have to answer before you start creating a bill of material (BOM)? Note: There are 2 correct answers to this question.

Options:

A.

In which storage location is the BOM required?

B.

Is the material type allowed in the BOM?

C.

Which base unit of measure does the material have?

D.

What status does the BOM have?

Question 23

You have a scheduling agreement with a vendor. You want classic MRP to automatically create schedule lines in case of material shortage. What must you do?

Note: There are 2 correct answers to this question.

Options:

A.

Set the creation indicator for purchase requisitions on the initial screen of the MRP run.

B.

Add the agreement to the source list mark it for MRP relevance.

C.

Set the creation indicator for delivery schedule lines on the initial screen of the MRP run.

D.

Add the agreement to the quota arrangement mark it for MRP relevance.

Question 24

Which chart types does the tabular planning table for capacity planning provide in SAP S/4HANA Cloud Private Edition?

Note: There are 2 correct answers to this question.

Options:

A.

Order (pool) chart

B.

Capacity requirements chart

C.

Orders (dispatched) chart

D.

Work center capacities chart