In your plant MRP is activated.
Which options do you have to exclude a material from the MRP run? Note: There are 2 correct answers to this question.
What can you use stard heuristics in Advanced Planning (PP/DS) for?
What could be the reason for different combinations of components in a multiple bill of material (BOM)? Note: There are 2 correct answers to this question.
Where do you maintain the work center that represents the production line for repetitive manufacturing? Note: There are 2 correct answers to this question.
Advanced Planning uses master data from SAP S/4HANA Cloud Private Edition. In which data objects can you set the Advanced Planning flag? Note: There are 2 correct answers to this question.
How can you set up a material as a phantom assembly? Note: There are 2 correct answers to this question.
Which information is required when you create a product master in SAP S/4HANA Cloud Private Edition? Note: There are 2 correct answers to this question.
Under what circumstances can you change the material type for a material if stocks reservations or purchasing documents exist? Note: There are 2 correct answers to this question.
What could be the reason for multiple commitments where several operations have the same scheduled dates on a work center after dispatching? Note: There are 2 correct answers to this question.
Your company produces a finished good based on a forecast expects it to be in stock when customers order it. If customers order more than the forecasted quantity this must NOT have any impact on the production program.
Which planning strategy do you use?
Your production planners are allowed to execute planning only for specific resources. How can you achieve this in Advanced Planning (PP/DS)?
Which of the following automation options can you use for production orders? Note: There are 2 correct answers to this question.
Which time elements are relevant for lead time scheduling of a production order? Note: There are 2 correct answers to this question.
How can you limit the validity of a bill of material (BOM)? Note: There are 2 correct answers to this question.
Your company manufactures materials whose characteristics differ for each manufacturing process.
Which application do you have to use in SAP S/4HANA Cloud Private Edition to be able to track use this information in all areas of logistics?
Which stard item categories can you select inside a bill of material (BOM)? Note: There are 2 correct answers to this question.
You use planning strategy Finite Scheduling with Reverse want to allow scheduling in the past. How can you parameterize this in the strategy profile?
What are the options if the Dispatched operation status is set for a production order operation? Note: There are 2 correct answers to this question.
Which actions does the system perform by default when you save a confirmation for a finished product in repetitive manufacturing? Note: There are 3 correct answers to this question.
What data can you maintain in the subitems of a bill of material (BOM)? Note: There are 2 correct answers to this question.
You are trying to create a production order NO valid production version can be selected. What could be the reasons? Note: There are 2 correct answers to this question.
Which of the following questions do you have to answer before you start creating a bill of material (BOM)? Note: There are 2 correct answers to this question.
You have a scheduling agreement with a vendor. You want classic MRP to automatically create schedule lines in case of material shortage. What must you do?
Note: There are 2 correct answers to this question.
Which chart types does the tabular planning table for capacity planning provide in SAP S/4HANA Cloud Private Edition?
Note: There are 2 correct answers to this question.