In SAP S/4HANA, during the creation of planned orders or production orders, the system relies on specific master data to determine the production process, components, and operations. The system checks the following:
In the bill of material (BOM)(C): The BOM (maintained in transaction CS01/CS02) defines the components required for production. MRP explodes the BOM to generate dependent requirements for planned orders, and production orders inherit this structure. The BOM’s validity (e.g., date, lot size) and usage (e.g., production) are verified during order creation.
In the MRP controller(D): The MRP controller (material master, MRP 1 view, field: MRP Controller) influences master data selection indirectly through its configuration in Customizing (e.g., Production > Material Requirements Planning > Master Data > Define MRP Controllers). It can determine planning parameters and production versions, affecting order creation.
In the routing(E): The routing (maintained in transaction CA01/CA02) specifies the operations, sequence, and work centers for production. During order creation, the system selects the routing to define the production process, ensuring the correct operations are assigned to the order.
In the production version(A) is critical for linking BOMs and routings, but the system checks within the BOM and routing directly once the version is selected, not the version itself as a "check location."In the work centers(B) provides capacity and scheduling data, but the system does not check master data selection settings there—it uses the routing to reference work centers. This aligns with SAP’s production planning master data integration.
[References:SAP S/4HANA Cloud Private Edition - Production Planning and Manufacturing, Unit: Master Data for Production Planning, SAP Help Portal: "BOM and Routing in Order Creation" (https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/), "MRP Controller Settings.", ]