Which of the following can be derived automatically when you carry out scheduling in projects with networks?
There are 2 correct answers to this question.
Response:
Which statements about project coding mask are true?
There are 3 correct answers to this question.
Response:
When the system derives settlement rules, it generates profitability segments that contain the characteristic values of which of the following assigned to them?
There are 2 correct answers to this question.
Response:
What are the various transactions in SAP PS with which a work breakdown structure can be created?
There are 3 correct answers to this question.
Response:
Assume you have created a sales order for a material to which a strategy group for assembly processing has been assigned and the system automatically created a so-called assembly order in the background and started assembly processing.
In this case, the assembly processing omits which stage and generates an operative order directly from the sales order?
Please choose the correct answer.
Response:
What are the three areas of the project screen?
There are 3 correct answers to this question.
Response:
Which parameters determine if the network header or network activities are cost objects?
There are 2 correct answers to this question.
Response:
Which of the following decides whether networks can be header assigned or activity-assigned?
There are 2 correct answers to this question.
Response:
What is the flag used for WBS elements for which you want to plan costs?
Please choose the correct answer.
Response:
In which type of billing the total value to be billed is apportioned to individual dates in the billing plan according to defined rules?
Please choose the correct answer.
Response:
To link customer inquiry in SD to the project system, you need to assign one or more inquiry items to which of the WBS element?
There are 2 correct answers to this question.
Response:
Which indicator do you use to define the characteristics of a WBS element and to specify tasks that are performed by the WBS element when the project is executed?
Please choose the correct answer.
Response:
What are the different options available for project stock?
There are 3 correct answers to this question.
Response:
Which of the following scenario doesn’t allow the plan value of the order to be added to the committed value of the WBS element until the order has the status released?
Please choose the correct answer.
Response:
Which of the following prerequisites need to be met in order to analyze the capacity requirements of an activity?
There are 3 correct answers to this question.
Response:
What is the procurement element for requirements planning?
Please choose the correct answer.
Response:
How does a project manager plan resources in cProjects and define responsibilities for different objects?
There are 2 correct answers to this question.
Response:
What are the different views available for capacity planning and work center planning?
There are 2 correct answers to this question.
Response:
Consider a scenario in easy cost planning where you plan dates and resources in network activities and the system automatically determines the corresponding planned costs as part of network costing.
In this scenario planned costs are determined for which of the following?
There are 3 correct answers to this question.
Response:
In which type of billing do you assign the posting to the down payment request when you post the incoming payment for a down payment?
Please choose the correct answer.
Response:
Which SAP standard item category always leads to direct procurement and a purchase requisition generated by the network?
Please choose the correct answer.
Response:
Which of the following allows you to view project objects with key performance data for quick analysis and update the percentage complete for earned value calculations?
Please choose the correct answer.
Response:
If the material is not assigned to any sales order or project and are available for use by general plant requirements. We consider this under which type of stock?
There are 2 correct answers to this question.
Response:
Which type of billing is generally used in plant engineering and construction projects?
Please choose the correct answer.
Response: