Winter Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

Pass Using C_TPLM22_67 Exam Dumps

Page: 6 / 6
Total 165 questions

SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 Questions and Answers

Question 21

Which SAP standard item category always leads to direct procurement and a purchase requisition generated by the network?

Please choose the correct answer.

Response:

Options:

A.

Non-stock item

B.

Stock item

C.

Billing item

D.

Non-billing item

Question 22

Which of the following allows you to view project objects with key performance data for quick analysis and update the percentage complete for earned value calculations?

Please choose the correct answer.

Response:

Options:

A.

Project reporting

B.

Progress analysis work bench

C.

Project analysis Team View

D.

Project progress analysis

Question 23

If the material is not assigned to any sales order or project and are available for use by general plant requirements. We consider this under which type of stock?

There are 2 correct answers to this question.

Response:

Options:

A.

Plant stock

B.

Project stock

C.

General stock

D.

Sales order stock

Question 24

Which type of billing is generally used in plant engineering and construction projects?

Please choose the correct answer.

Response:

Options:

A.

Periodic billing

B.

Project billing

C.

Milestone billing

D.

Fixed billing

Page: 6 / 6
Total 165 questions