Question 5

Testing Process

Which of the following statements describing the consequences of specifying test conditions at a detailed level is NOT true?

Number of correct responses: 1

K21 credit

Options:

A.

In an environment where the test basis is continuously changing, it is recommended to specify test conditions at a detailed level in order to achieve a better maintainability

B.

The specification of test conditions at a detailed level can be effective when no formal requirements or other development work products are available

C.

The specification of test conditions at a detailed level can require the implementation of an adequate level of formality across the team

D.

For system testing, the specification of test conditions at a detailed level, carried out early in the project as soon as the test basis is established, can contribute to defect prevention

Question 6

People Skills – Team Composition

Assume you are managing the system testing execution phase of a project.

The system test execution period for that project is scheduled for eighteen weeks and the release date is scheduled at the end of system testing.

During the sixth week of system test execution, at the staff meeting, the project manager informs you that the project deadlines are changed and the release date that is only three weeks ahead.

This new release will not allow the completion of the system tests. Suppose also that you have followed a risk-driven test approach for this project.

Which of the following statements represents the worst way to lead your test team in the next three weeks?

Number of correct responses: 1

K21 credit

Options:

A.

Neglect your management activities and work side-by-side with your test team executing tests

B.

Considering the executed tests, you should reduce the test coverage back on the risk analysis and adjust downward the priority of the associated risk items

C.

Convince all the people of your test team that each of them is an important and needed member, and that their contribution is fundamental to the success of the team

D.

Favor and encourage a proactive attitude where people ask for new tasks as soon as they finish their current tasks

Question 7

People Skills – Team Composition

An agile development team decides to hire a tester who has always worked:

- in independent test teams, reporting the problems found in a defect tracking system

- in safety-critical projects, with a stronger focus on the quality of the product than on time and budget.

This agile team is focused on short-term goals to get the product released on time and within budget.

Which of the following answers would you expect to be most likely true in this scenario?

Number of correct responses: 1

K21 credit

Options:

A.

Agile teams like the presence of a tester in their teams and the tester will be able to adapt to the new context without any issue

B.

The developers will immediately follow the guidelines described by the tester

C.

The tester can continue to report the problems found in a defect tracking system and be more focused on the quality than on time and budget constraints

D.

The tester’s mission could be to verify adherence to requirements, instead of reporting formally the problems in a defect tracking system

Question 8

People Skills – Team Composition

Which of the following would you expect to be most likely an example of a motivating factor for testers?

Number of correct responses: 1

K21 credit

Options:

A.

The resources allocated for the testing activities are not sufficient and don’t allow the testers to contribute to the quality of the product

B.

The testers contribution to the quality of the software products developed from an organization is recognized with increased responsibilities

C.

The same regressions tests are executed manually by the same testers, for every product release, without any progression in content

D.

The testers are asked to perform, in parallel with their testing tasks, other tasks unrelated to their testing responsibilities