Professional Scrum with Kanban (PSK 1) Exam Questions and Answers

Question 9

Which of the following metrics are likely to be reviewed during flow-based Daily Scrum?

(choose the best two answers)

Options:

A.

Work Item Age.

B.

Work in Progress (WIP).

C.

Process control chart and Scrum Team's 85th percentile.

D.

Lead Time.

E.

Throughput.

F.

Cycle Time.

G.

Velocity.

Question 10

A service level expectation (SLE) consists of which two items?

(choose the best two answers)

Options:

A.

A cost of delay.

B.

A probability.

C.

A forecasted date.

D.

A period of elapsed days.

Question 11

Little's Law states that:

(choose the best answer)

Options:

A.

Average Cycle Time = Average Work in Progress / Average Throughput.

B.

Average Throughput = Average Cycle Time * Average Work in Progress.

C.

Average Work in Progress = Average Cycle Time / Average Throughput.

D.

Average Throughput = Average Cycle Time / Average Work in Progress.

Question 12

True or False: The primary effect of limiting Work in Progress (WIP) is that it creates a pull

system.

Options:

A.

True

B.

False