Question 5

Which object is relevant in assembly processing to create an assembly order for the SD document?

Options:

A.

Project profile

B.

Item category

C.

Requirement class

D.

Control key

Question 6

Project Structure

Which statement regarding the creation of a new work breakdown structure (WBS element) are true?

Note : there are 3 correct answer for this question.

Options:

A.

You can create several WBS elements per level.

B.

A new work breakdown structure must contain up to 10 levels.

C.

A WBS element of the new project can be assigned to a different project definition.

D.

WBS element can be a planning element, an account assignment element, and a billing element at the same time.

E.

The WBS structure can contain several level 1 WBS element, (es configurable por perfil de proyecto)

Question 7

Which of the following actions can transfer actual costs for external processing? Note: There are 2 correct answers to this question

Options:

A.

Saving a supplier invoice

B.

Saving a service entry shee

C.

Saving a goods receipt

D.

Saving a purchase order

Question 8

Which of the following factors influence the scheduling of internal processing activities? Note: There are 3 correct answers to this question

Options:

A.

An activated Scheduling indicator in the control key of the internal processing activity

B.

Whether the work for the internal activity is greater than its duration

C.

The unit (for example, hour, day) of the field Normal Duration field of the activity

D.

The relationships between activity elements

E.

The factory calendar in the work center used for the internal processing activity