Summer Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

SAP Certified Associate C_S4TM_2023 Syllabus Exam Questions Answers

Page: 7 / 15
Total 197 questions

SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Transportation Management Questions and Answers

Question 25

The Core Interface or CIF is the technology that is used to transfer the master data from ERP to TM. Master data inormally scheduled for batch transfer once a day. The transfer of master data changes can be scheduled periodically as a job. You have to define a variant (containing the target system -TM - and the selection of master data objects) for the program RCPTRAN4 (hidden behind transaction CFP1).

Before you transfer the master-data, the following prerequisites need to be satisfied:

(2 correct answers)

Options:

A.

For sales orders , destination locations are stored on root level

B.

You have completed the SAP TM system configuration to connect to the SAP ERP system, since SAP TM can be integrated with your SAP ERP system , SAP TM needs to know the physical location and client of the SAP ERP system to which it will transmit planning and execution data

C.

You have completed the SAP ERP system configuration to connect to the SAP TM system, this define the specific server and client to which SAP ERP will transmit the data

Question 26

You have implemented a side-by-side scenario of SAP Transportation Management and SAP S/4HANA. Which of the following statements apply to the organizational units in SAP Transportation Management?

Note: There are 2 correct answers to this question.

Options:

A.

The hierarchical relationship of organizational units is not fixed

B.

Organizational units can be determined automatically based on conditions

C.

Organizational units can be maintained independently of organizational units in SAP S/4HANA

D.

Organizational units are not mandatory

Question 27

The following settings are defined for a freight order from location A to location B with two freight units:

* The distance between locations A and B in the transportation lane is 1500 km, the duration is 19 hours and the Fix Transportation Duration flag is set. The average speed for the means of transport is defined as 100 km/h and the GIS quality flag is NOT set.

Loading and unloading of each freight unit at locations A and B is defined as 1 hour.

The vehicle resource is available weekdays from 8:00 am to 8:00 pm.

• Loading starts on Monday at 8:30 am. When is unloading finished?

Please choose the correct answer.

Options:

A.

Tuesday 7:30 pm

B.

Tuesday 5:30 pm

C.

Tuesday 7:30 am

D.

Tuesday 3:30 pm

Question 28

You want to print a road waybill document, a loading list, and labels for your freight orders with freight order type FOT1. You also want to send e-mails and XML messages to the carriers of freight orders of this type. What is the MINIMUM number of PPF action profiles that you need to define for this purpose?

Options:

A.

1

B.

4

C.

2

D.

3

Page: 7 / 15
Total 197 questions