Total 80 questions

SAP Certified Associate - Project Manager - SAP Activate Questions and Answers

Question 13

What technique helps a Scrum team to prioritize a large, flat backlog? Note: There are 2 correct answers to this question.

Options:

A.

Splitting the backlog into epics

B.

MOSCOW prioritization

C.

A/B testing user stories

D.

User story mapping

Question 14

Which SAP products relate to the scenarios included in the SAP Activate roadmap for the Intelligent Enterprise? Note: There are 3 correct answers to this question.

Options:

A.

SAP Fieldglass

B.

SAP Integrated Business Planning for Supply Chain

C.

SAP S/4HANA Cloud

D.

SAP Concur

E.

SAP Sales Cloud

Question 15

Which of the following tools are considered enablers for digital transformation? Note: There are 3 correct answers to this question.

Options:

A.

SAP Product Availability Matrix

B.

SAP Roadmap Viewer

C.

Software Logistics Toolset

D.

SAP Activate Community

E.

SAP Signavio Process Navigator

Question 16

What are the responsibilities of the product owner in release and sprint planning? Note: There are 2 correct answers to this question.

Options:

A.

Estimate the backlog user stories.

B.

Define objectives for each release.

C.

Analyze the functional and technical dependencies between user stories.

D.

Prioritize backlog user stories by business priority.