SAP Certified Associate - Project Manager - SAP Activate Questions and Answers

Question 21

What criteria does the Scrum team use to sequence the product backlog? Note: There are 2 correct answers to this question.

Options:

A.

Length of the sprint

B.

Business priority

C.

Experience of team members

D.

Technical dependencies

Question 22

What tool would you use for managing project tasks and Solution Documentation when implementing SAP S/4HANA Cloud, public edition?

Options:

A.

SAP Cloud ALM

B.

SAP Signavio Process Navigator

C.

SAP Roadmap Viewer

D.

SAP Transformation Navigator

Question 23

Which of the following cloud services are available on SAP Business Technology Platform? Note: There are 3 correct answers to this question.

Options:

A.

SAP Integration Suite

B.

SAP HANA Cloud

C.

SAP Cloud ALM

D.

SAP Data Migration Cockpit

E.

SAP Master Data Governance

Question 24

When does the Scrum team receive formal confirmation that the user stories are completed to the satisfaction of the product owner?

Options:

A.

During the sprint review

B.

During the sprint retrospective

C.

During the sprint backlog review

D.

During the sprint user acceptance test