New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PDF H19-424_V1.0 Study Guide

HCSP-Presales-Campus Network Planning and Design V1.0 Questions and Answers

Question 25

Which of the following cannot be used as the basis for the recognition of the WLAN delivery capability of the channel for a channel delivery project?

Options:

A.

WLAN product delivery qualification. Such as HCIA or HCIP engineers

B.

Huawei's WLAN project delivery experience

C.

Friend's experience in delivering non-WLAN projects

D.

Competitor WLAN project delivery qualification and experience

Question 26

In the virtualization scenario, we recommend using () external network design when using a unified access policy for different VNs

Options:

A.

L3 shared exit

B.

L3 exclusive export

C.

L2 shared exit

D.

L2 exclusive export

Question 27

In the WLAN Planner tool, under what circumstances will it not prompt whether to enter roaming mode when walking on the 3D floor

Options:

A.

The number of APs is greater than 50 or equal to 0

B.

The number of APs is greater than 100 or equal to 0

C.

When the signal strength in the floor is too low

D.

In the case of insulating obstacles

Question 28

In the V200R022 version of the S switch, the description of the S5X31(S)-S multi-rate switch is wrong ()

Options:

A.

Support 2G large cache to cope with high burst business traffic.

B.

It can be used as a remote module for the central switch to achieve simplified networking.

C.

It supports advanced features such as VxLAN and MPLS, real-time telemetry data collection, and network O&M visualization, which can be widely used in scenarios such as medium-sized campus aggregation and small campus cores.

D.

3 power supply design, support N+1 redundancy, full 802.3bt90W PoE++ power supply for all ports, and the maximum PoE output power of the whole machine can reach 2268W, adapting to the power supply needs of massive terminals.