Winter Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

Passed Exam Today 1z0-1075-24

Page: 2 / 4
Total 50 questions

Oracle Manufacturing Cloud 2024 Implementation Professional Questions and Answers

Question 5

Which statement is NOT true about cumulative lead time?

Options:

A.

It calculates cumulative manufacturing lead times by rolling up manufacturing lead times of make Items.

B.

It updates the item's lead time attributes at the end of the calculation process: cumulative manufacturing and cumulative total lead times.

C.

It calculates cumulative total lead times by rolling up lead times of make items and adding up lead time values of buy items.

D.

It updates lead time percent at the operation level in the work definition.

Question 6

In a manufacturing plant, two purchase components, PI and P2, and a resource, Rl, are required to assemble a product. The cost of the assembly is calculated by using the standard costing method. The work definition and resource rates for the assembly have been defined as Required.

A Cost Accountant is estimating cost of the assembly, and analyzing rolled-up costs before finally publishing estimates as frozen standards to Cost Accounting by using a Cost Planning Scenario. While reviewing rolled-up costs, the extended costs of purchase components are not included in a rolled-up scenario.

What is the reason for this?

Options:

A.

Costs for purchase components PI and P2 are not defined In Cost Accounting.

B.

Purchase components PI and P2 are not associated with the material cost plan of the Cost Planning Scenario.

C.

Create Accounting was not initiated.

D.

Create Accounting Distributions was not initiated.

Question 7

A manufacturing plant works in two shifts of eight hours each. A Manufacturing user wants four units of a work center resource, R1, to be available during nonworking time, outside the regular shift on a particularday.

Which is the correct sequence of steps to create a resource exception on the Manage Work Center Resource Calendar page?

Options:

A.

Click Inside the existing shift time on a specific date > Go to the Create Work Center page > Click the Resource Availability tab > Click the Add icon > Select R1 from the Resource dropdown list > Enter 4 in Default Units Available.

B.

Click inside the existing shift time on a specific date > Go to the Actions menu > Select Create Resource Exception > Populate the Start and Duration Fields > Go to the Resource Availability region > Populate A units in the Default Availability column.

C.

Click outside the existing shift time on a specific date > Go to the Actions menu > Select Create Resource Exception > Populate the Start and Duration fields > Go to the Resource Availability and Overrides region > Populate 4 units in the Availability Override column.

D.

Click outside the existing shift time on a specific date > Go to the Create Work Center page > Click the Resource Availability tab > Click the Add icon > Select R1 from the Resource drop-

Question 8

Your client is planning to override the Plant Production Calendar with One or More Date-Effective Work Center Calendars. You need to explain the consideration when using the Override the Plant Production Calendar with One or More Date-Effective Work Center Calendars feature.

Which three statements are true when overriding the production calendar?

Options:

A.

The Work Execution Work Area Infolets and Manage Production Exceptions page are based on the plant calendar and not on work center calendars.

B.

While defining override calendars, you need to ensure that the date effective range for a work center calendar association can be overlapping and contiguous.

C.

Even if there are override calendars, the lead time calculation in days for an item remains based on the plant calendar and not on work center calendars.

D.

When the user executes search action in the Review Dispatch List page, if more than one work center are selected and if the start date or completion date is based on Shift-based search, then the operations are queried based on the shifts of the plant calendar only.

E.

Supplier operations used in outside processing use the work center calendar in work order scheduling.

Page: 2 / 4
Total 50 questions