New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

New Release CTAL-TM Test Manager Advanced Questions

Page: 2 / 5
Total 65 questions

Certified Tester Advanced Level Test Manager (CTAL-TM) Questions and Answers

Question 5

You are the Test Manager of a four-person test team working for a small distribution company with a single warehouse. Your team has been working with a third party development team on a new

inventory management system. The company expects this system to generate approximately one million dollars per annum in profits for the company. Early in the project, various risks were

identified, and steps taken to mitigate those risks.

For example, you sent your test team for training on the new system, and upgraded the test environment. There are still some lingering risks that have not been addressed, but they have been

determined to have a low chance of occurring, with minimal impact if they do occur.

What would be the best option to mitigate these remaining risks? [3]

Options:

A.

Note the risks, and ignore them for now.

B.

Redo the project test plan to add additional testing for these risk items.

C.

Contract with the Risk Protection Insurance company to assume these risks at a cost of $500,000 per annum.

D.

Create a cross-functional team to work to reduce the impact and likelihood of these risks coming to fruition.

Question 6

Your Project Manager has challenged you to come up with a process improvement strategy using the IDEAL model.

Which step within the process defines the success criteria? [2]

Options:

A.

Entrance

B.

Analysis

C.

Diagnosing

D.

Initiation

Question 7

Which of the following is a typical use of risk analysis? [1]

Options:

A.

Identifying the appropriate depth of testing for each identified risk

B.

Deciding what personnel should be assigned to which tests

C.

Determining the design of the tests used to mitigate each identified risk

D.

Forecasting the product delivery date

Question 8

You have been carefully monitoring the progress of testing for your project. You have been using the established traceability to verify that the requirements and test

conditions are being adequately addressed. The test team is proceeding well in their test case execution and you can see that you are achieving about 80% coverage of

the test conditions per the traceability mapping in your test management system. You have seen a number of defects being logged against test conditions that are failing,

but you do not see a mapping of the test cases to those conditions.

What is likely to be occurring in the testing area that is causing the traceability to break down? [2]

Options:

A.

The test cases are mapped to the test strategy and are bypassing the test conditions.

B.

The testers are running exploratory tests that are not mapped to the test conditions.

C.

The testers are executing the wrong tests.

D.

The testers are not updating the test execution information in the test management system.

Page: 2 / 5
Total 65 questions