Last Attempt Prince2-Practitioner Questions

PRINCE2 Practitioner Exam Questions and Answers

Question 5

While preparing the Configuration Management Strategy, the Project Manager considered the options for change control. He decided to recommend a change budget of £250k, but was undecided on the Change Authority to recommend.

Which option is an appropriate Change Authority for the Outsourcing project?

Options:

A.

The selected service provider to approve and implement all changes.

B.

Senior User(s) and Project Assurance representatives, within the limits of the recommended change budget.

C.

The Director of Facilities and the Director of Information Technology to approve all changes.

Question 6

Scenario

Additional Information

Extract from the Communication Management Strategy.

The project information in the table below is true, but it may not be recorded under the correct heading or be in the correct document.

Using the Project Scenario, select the appropriate response to each of the following 5 questions which have been raised by the Project Board.

The project is now at the end of the initiation stage. Having decided that the Calendar project is a relatively simple project, the Project Manager combined the Starting Up a Project process and the Initiating a Project process. No Project Brief has been produced. Instead the Project Manager used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO includes the Business Case, a product checklist and several Product Descriptions, Including the Project Product Description. Short sections are also included for each of the strategies and the controls to be applied. The Project Manager has elected to use the Daily Log to record all risks, issues, lessons and quality - results.

After the initiation stage there will be two further stages during which a small number of Work Packages will be authorized. While these are being managed, the Project Manager will hold regular checkpoints, which will support the production of weekly Highlight Reports to the Project Board.

This question provides a number of changes which may or may not be required to the Extract from the Communication Management Strategy provided in the additional information.

What statement applies to the Records section?

Options:

A.

Move entry 6 to the Configuration Management Strategy because it defines the identification scheme for the project's products.

B.

Move entry 7 to Communication procedure because it refers to the method to be used for communication to external parties.

C.

Move entry 8 to Tools and techniques because it refers to a filing technique.

Question 7

Scenario

Additional Information

Extract from the Communication Management Strategy.

The project information in the table below is true, but it may not be recorded under the correct heading or be in the correct document.

Using the Project Scenario, select the appropriate response to each of the following 5 questions which have been raised by the Project Board.

The project is now at the end of the initiation stage. Having decided that the Calendar project is a relatively simple project, the Project Manager combined the Starting Up a Project process and the Initiating a Project process. No Project Brief has been produced. Instead the Project Manager used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO includes the Business Case, a product checklist and several Product Descriptions, Including the Project Product Description. Short sections are also included for each of the strategies and the controls to be applied. The Project Manager has elected to use the Daily Log to record all risks, issues, lessons and quality - results.

After the initiation stage there will be two further stages during which a small number of Work Packages will be authorized. While these are being managed, the Project Manager will hold regular checkpoints, which will support the production of weekly Highlight Reports to the Project Board.

This question provides a number of changes which may or may not be required to the Extract from the Communication Management Strategy provided in the additional information.

Which statement applies to the Timing of communication activities section?

Options:

A.

Delete entry 9 because activities for controlling the project should be planned as part of Project controls in the Project Initiation Documentation.

B.

No change to entry 9 because it describes the timing of performance reports.

C.

Delete entry 10 because Highlight Reports are a Project Board control, the frequency of which should be recorded in the Project controls section of the Project Initiation Documentation.

Question 8

Which statement is an appropriate entry for the project approach heading within the Project Brief?

Options:

A.

The initial estimates from the feasibility study will be verified during the initiation stage.

B.

MFH must better manage suppliers' performance.

C.

The Information Technology Division and the Facilities Division will be outsourced to a single service provider.

D.

The Project Manager will be responsible for ensuring that the agreed project approach remains an appropriate choice.