Month End Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Prince2-Practitioner Exam Dumps : PRINCE2 Practitioner Exam

PDF
Prince2-Practitioner pdf
 Real Exam Questions and Answer
 Last Update: Jan 23, 2025
 Question and Answers: 282
 Compatible with all Devices
 Printable Format
 100% Pass Guaranteed
$25.5  $84.99
Prince2-Practitioner exam
PDF + Testing Engine
Prince2-Practitioner PDF + engine
 Both PDF & Practice Software
 Last Update: Jan 23, 2025
 Question and Answers: 282
 Discount Offer
 Download Free Demo
 24/7 Customer Support
$40.5  $134.99
Testing Engine
Prince2-Practitioner Engine
 Desktop Based Application
 Last Update: Jan 23, 2025
 Question and Answers: 282
 Create Multiple Test Sets
 Questions Regularly Updated
  90 Days Free Updates
  Windows and Mac Compatible
$30  $99.99
Last Week Results
32 Customers Passed PRINCE2
Prince2-Practitioner Exam
Average Score In Real Exam
86.7%
Questions came word for word from this dump
88.6%
PRINCE2 Bundle Exams
PRINCE2 Bundle Exams
 Duration: 3 to 12 Months
 2 Certifications
  4 Exams
 PRINCE2 Updated Exams
 Most authenticate information
 Prepare within Days
 Time-Saving Study Content
 90 to 365 days Free Update
$249.6*
Free Prince2-Practitioner Exam Dumps

Verified By IT Certified Experts

CertsTopics.com Certified Safe Files

Up-To-Date Exam Study Material

99.5% High Success Pass Rate

100% Accurate Answers

Instant Downloads

Exam Questions And Answers PDF

Try Demo Before You Buy

Certification Exams with Helpful Questions And Answers

PRINCE2 Practitioner Exam Questions and Answers

Question 1

Which of the following principles uses Product Descriptions to provide clarity by defining each product's purpose, composition, derivation, format, quality criteria and quality method?

Options:

A.

Tailor to suit the project environment

B.

Focus on products

C.

Manage by stages

D.

Continued business justification

Buy Now
Question 2

Scenario

Additional Information

Extract from the Communication Management Strategy.

The project information in the table below is true, but it may not be recorded under the correct heading or be in the correct document.

Using the Project Scenario, select the appropriate response to each of the following 5 questions which have been raised by the Project Board.

The project is now at the end of the initiation stage. Having decided that the Calendar project is a relatively simple project, the Project Manager combined the Starting Up a Project process and the Initiating a Project process. No Project Brief has been produced. Instead the Project Manager used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO includes the Business Case, a product checklist and several Product Descriptions, Including the Project Product Description. Short sections are also included for each of the strategies and the controls to be applied. The Project Manager has elected to use the Daily Log to record all risks, issues, lessons and quality - results.

After the initiation stage there will be two further stages during which a small number of Work Packages will be authorized. While these are being managed, the Project Manager will hold regular checkpoints, which will support the production of weekly Highlight Reports to the Project Board.

This question provides a number of changes which may or may not be required to the Extract from the Communication Management Strategy provided in the additional information.

What statement applies to the Records section?

Options:

A.

Move entry 6 to the Configuration Management Strategy because it defines the identification scheme for the project's products.

B.

Move entry 7 to Communication procedure because it refers to the method to be used for communication to external parties.

C.

Move entry 8 to Tools and techniques because it refers to a filing technique.

Question 3

The chair of a quality review meeting advised the Team Manager that, because there were so many major issues, the product had been rejected. The presenter estimated that the corrections would take about two weeks. The re-assessment of the product will take a further week, resulting in a three-week delay. The Work Package only has one week tolerance.

Which 2 actions should the Team Manager take in response to this situation?

Options:

A.

Ask the reviewers to work overtime to prevent the delay.

B.

Ensure that the situation is included in the next Highlight Report.

C.

Raise an issue explaining that tolerances are forecast to be exceeded.

D.

Advise the Project Manager of the risk that there may be a two-week delay in the delivery of one of the products.

E.

Ensure that the Quality Register is updated with the quality review result.