New Year Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Prince2-Practitioner Exam Dumps : PRINCE2 7 Practitioner (7th Edition) Exam

PDF
Prince2-Practitioner pdf
 Real Exam Questions and Answer
 Last Update: Jan 12, 2026
 Question and Answers: 263 With Explanation
 Compatible with all Devices
 Printable Format
 100% Pass Guaranteed
$25.5  $84.99
Prince2-Practitioner exam
PDF + Testing Engine
Prince2-Practitioner PDF + engine
 Both PDF & Practice Software
 Last Update: Jan 12, 2026
 Question and Answers: 263
 Discount Offer
 Download Free Demo
 24/7 Customer Support
$40.5  $134.99
Testing Engine
Prince2-Practitioner Engine
 Desktop Based Application
 Last Update: Jan 12, 2026
 Question and Answers: 263
 Create Multiple Test Sets
 Questions Regularly Updated
  90 Days Free Updates
  Windows and Mac Compatible
$30  $99.99
Last Week Results
32 Customers Passed PRINCE2
Prince2-Practitioner Exam
Average Score In Real Exam
86.7%
Questions came word for word from this dump
88.6%
PRINCE2 Bundle Exams
PRINCE2 Bundle Exams
 Duration: 3 to 12 Months
 3 Certifications
  5 Exams
 PRINCE2 Updated Exams
 Most authenticate information
 Prepare within Days
 Time-Saving Study Content
 90 to 365 days Free Update
$249.6*
Free Prince2-Practitioner Exam Dumps

Verified By IT Certified Experts

CertsTopics.com Certified Safe Files

Up-To-Date Exam Study Material

99.5% High Success Pass Rate

100% Accurate Answers

Instant Downloads

Exam Questions And Answers PDF

Try Demo Before You Buy

Certification Exams with Helpful Questions And Answers

PRINCE2 Prince2-Practitioner Exam Dumps FAQs

Q. # 1: What is the Prince2-Practitioner Exam?

The Prince2-Practitioner Exam assesses your ability to apply and tailor the PRINCE2 methodology in real project scenarios. It's designed for experienced project managers looking to enhance their skills.

Q. # 2: Who should take the Prince2-Practitioner Exam?

The Prince2-Practitioner exam is ideal for project managers, team leaders, and professionals seeking to advance their careers in project management. It's particularly relevant for those working in industries that heavily rely on structured project management approaches.

Q. # 3: What topics are included in the Prince2-Practitioner Exam?

The Prince2-Practitioner exam covers PRINCE2 principles, themes, processes, and practices, including project initiation, planning, execution, and closure.

Q. # 4: How many questions are on the Prince2-Practitioner Exam?

The Prince2-Practitioner exam consists of 68 multiple-choice and multiple-response questions.

Q. # 5: How long is the Prince2-Practitioner Exam?

The Prince2-Practitioner exam duration is 2.5 hours.

Q. # 6: What is the passing score for the Prince2-Practitioner Exam?

You need to score at least 55% to pass the Prince2-Practitioner exam.

Q. # 7: What is the difference between PRINCE2 Prince2-Practitioner and Prince2-Foundation Exams?

The PRINCE2 Foundation and PRINCE2 Practitioner exams serve different purposes and are tailored to different levels of understanding and application of the PRINCE2 methodology.

  • Prince2-Practitioner Exam: The Prince2-Practitioner Exam goes beyond theory, assessing your ability to apply and tailor PRINCE2 to real-world project scenarios. It evaluates your practical skills in managing projects using PRINCE2 principles and adapting them to various situations.
  • Prince2-Foundation Exam: The Prince2-Foundation Exam focuses on the fundamental principles, themes, and processes of the PRINCE2 methodology. It tests your understanding of the terminology and basic concepts needed to work effectively in a project environment.

Q. # 8: How can CertsTopics help me prepare for the Prince2-Practitioner Exam?

CertsTopics offers Prince2-Practitioner PDFs and a testing engine with realistic questions and answers tailored to the Prince2-Practitioner Exam. With our Prince2-Practitioner study materials, you can practice thoroughly and increase your chances of passing on the first attempt.

Q. # 9: What is the success guarantee offered by CertsTopics for the Prince2-Practitioner Exam?

CertsTopics provides a success guarantee with our Prince2-Practitioner practice test. Our Prince2-Practitioner dumps materials are crafted to ensure that candidates have a thorough understanding of PRINCE2 concepts, significantly increasing their likelihood of passing the Prince2-Practitioner exam.

PRINCE2 7 Practitioner (7th Edition) Exam Questions and Answers

Question 1

It is now late October and the project is in stage 3. The label design competition has been held and the photos of the staff have been taken. The CEO and Marketing Director still need to choose the winning label design and the 12 photos for the calendar. However, the Executive has learned that two competitors are issuing calendars to MNO's customers by the middle of November. After analyzing the impact of this Issue, one of the options the Project Manager has presented to the Project Board is to close the project prematurely.

There are a number of key facts relating to this project that would need to be recorded if the project Y-e to be closed now.

Which product should register that the risk of a competitor producing a calendar at the same time was identified at the beginning of the project but the assessment of this risk appears to have been poor?

Options:

A.

Issue Register

B.

Follow-on action recommendations

C.

Lessons Report

D.

Risk Register

Buy Now
Question 2

Project Scenario

Calendar Project (Note: The companies and people within the scenario are fictional.)

There has been a reduction in fie number of orders at the MNO Manufacturing Company due in part to the increased marketing activities of its competitors. To help counter this, the company has decided to create a promotional calendar for next year for all its current and prospective customers. The end product of this project will be a prepared calendar pack, ready for printing. The design of the calendar will be similar to one sent out previously, and must reflect the company image as described in the existing corporate branding standards. Another project is currently producing a new company logo when is to be printed on each page of the promotional calendar. The prepared calendar pack will consist of:

    Design for each month - correctly showing at public holidays and new company logo

    Selected photographs- 12 professionally-produced photographs, showing different members of staff

    Selected paper and selected envelope - for printing and mailing the calendar

    Chosen label design - a competition to design a label will be held as part of this project

    List of customers - names and addresses of customers to whom the calendar will be sent.

The project is currently in initiation and will have two further stages:

Stage 2 will include tie activities to:

    Create the customer fast using information from the Accounts and Marketing departments

    Confirm compliance with the Data Protection Legislation

    Create a design for each month - this will be done by the internal creative team

    Select and appoint a professional photographer

    Gather photograph design ideas from previous project and agree photographic session schedule

    Prepare a production cost forecast

    Select paper and envelope.

Stage 3 will include the activities to:

    Produce and select tie professionally-taken photographs

    Hold the label design competition and choose the label design

    Assemble the prepared calendar pack.

A production cost forecast, based on the options and costs for the paper, envelope, printing and marketing of the calendar is to be produced in stage 2. However, the actual production and distribution of the calendars is not within the scope of the project. The product cost forecast will be reviewed by the Project Board to determine whether tie project should continue.

It is now 05 October and the prepared calendar pack must be delivered to the print company by 30 November, to enable printing and distribution of the calendar in time for Christmas. The cost of the activities to develop the specialist products and the cost of the project management activities are estimated to be £20,000. There is a project time tolerance of +1 week /-2 weeks and a project cost tolerance of +£6,000 / -£6,000. A change budget of £500 has been allocated but there is no risk budget.

During stage 2, if the Project Manager decides to recommend that the Project Plan is revised to finish three weeks later, which statement is correct?

Options:

A.

The tolerances stated in the Project Plan CANNOT be changed.

B.

The Executive needs to seek formal approval from corporate management to implement this change.

C.

The current project must close prematurely and be restarted with a new Project Plan, a new Business Case and new Risk Register.

D.

The revision of the Project Plan would have to wait until the end stage assessment of stage 2.

Question 3

Project Scenario – Health and Safety Training Project:

ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.

ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver “capability to provide health and safety training”, including the materials needed for classroom-based training and e-learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.

The e-learning course will be developed by a specialist external consultancy. The materials for classroom-based training will be delivered by ABC Company’s development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.

The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered. ABC Company is planning to deliver pilot courses within five months of starting the project.

The ABC Company standard development model for new courses recommends the following stages:

End of the Project scenario.

Additional Information:

The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.

The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.

The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.

The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company’s IT manager reports to the Operations Director.

The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.

The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.

The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.

The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.

The Corporate Document Manager reports to the Central Services Director. She helped establish the company’s document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.

The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.

End of the additional information.

The project board has asked for highlight reports every six weeks during stage 3. As a result, the project manager has asked each team manager for checkpoint reports every six weeks, in order to collate these into the highlight report. The team manager for the ‘marketed courses’ is new to team management.

Is this an appropriate action as part of the ‘controlling a stage’ process, and why?

Options:

A.

Yes, because the project board will need to be updated with the progress of every team.

B.

Yes, because checkpoint reports are a time-driven control providing progress information.

C.

No, because the frequency of reporting should reflect the level of control required for the work package.

D.

No, because the project board should decide on the frequency and content of progress reporting.