Pre-Summer Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

ISTQB ISTQB-CTAL-TA Actual Questions

ISTQB Certified Tester Advanced Level - Test Analyst (CTAL-TACore)v3.1.2 Questions and Answers

Question 21

Consider the following requirement:

The system shall allow cash advances of at least 200 Euros for all supported credit cards The following credit cards are supported- American Express, Diners, VISA, Mastercard and Eurocard.

The requirement has been identified as business critical.

The following test conditions have been derived:

1. The system shall allow cash advances of at least 200 Euros

2. It shall support American Express, Diners, VISA, Mastercard and Eurocard.

Assume you are following a risk-based testing strategy, where likelihood and impact are both assessed on a five-point scale ranging from very low to

very high The requirement R1 was identified as a risk item during the quality risk analysis process. In total 20 risk items were identified during this process

Assume that technical project stakeholders have assessed the likelihood of the requirement R1 risk item at a medium level Given only the information above, which of the following statements is true?

Options:

A.

The test cases associated with requirement R1 shall be run first in the test execution period

B.

The test cases associated with requirement R1 must be run towards the middle of the test execution period.

C.

A large number of test cases should be designed for requirement R1, based on impact

D.

The risk impact for requirement R1 should be categorized as high or very high

Question 22

Which TWO of the following are MOST likely to be defects found as part of portability testing?

a) Insufficient, unclear installation or de-installation instructions

b) Clumsy screen navigation and input screen labeling

c) Inability to log on as an administrator

d) Time out errors when entering incorrect login details

e) The stock control barcodes cannot be read by the replaced barcode scanner

SELECT ONE OPTION

Options:

A.

a, e

B.

a, d

C.

c, e

D.

b, d

Question 23

When would the Test Analyst’s involvement in an Agile project normally start?

SELECT ONE OPTION

Options:

A.

At the beginning of the first iteration

B.

As soon as the user stories have been signed-off

C.

In parallel with coding for the first iteration

D.

At the beginning of the project

Question 24

A PIN entry component of an ATM system has been developed using the following state table:

Using the state transition test technique, how many 0-switch test cases are needed to achieve 100% 0-switch coverage?

Options:

A.

4

B.

7

C.

8

D.

28