Question 13

Testing should be stopped when:

Options:

A.

All the planned tests have been run

B.

Time has run out

C.

All faults have been fixed correctly

D.

Both A and C

E.

It depends on the risks for the system being tested

Question 14

Which of the following is the main purpose of the component build and integration strategy?

Options:

A.

to ensure that all of the small components are tested

B.

to ensure that the system interfaces to other systems and networks

C.

to ensure that the integration testing can be performed by a small team

D.

to specify how the software should be divided into components

E.

to specify which components to combine when, and how many at once

Question 15

A new system is about to be developed. Which of the following functions has the highest level of risk?

Options:

A.

Likelihood of failure = 20%; impact value = £100,000

B.

Likelihood of failure = 10%; impact value = £150,000

C.

Likelihood of failure = 1%; impact value = £500,000

D.

Likelihood of failure = 2%; impact value = £200,000

Question 16

Which statement below BEST describes non-functional testing?

Options:

A.

The process of testing an integrated system to verify that it meets specified requirements.

B.

The process of testing to determine the compliance of a system to coding standards.

C.

Testing without reference to the internal structure of a system.

D.

Testing system attributes, such as usability, reliability or maintainability.